Construction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations

State-by-state comparison of the statutory rules governing retainage (retention) on construction contracts. Each record is one state with the maximum retainage percentage for public and private projects, the deadline for releasing retained funds after substantial completion, whether retainage must be held in an interest-bearing escrow account, whether the cap is reduced after a completion milestone (e.g. 50% complete), and the statutory citation. Caps range from 0% (New Mexico) to 10%, with a strong trend toward 5%. Answers 'how much retainage can be withheld on my project in [state]', 'when must retainage be released', and 'does my state require retainage escrow'.

Records30
Sources58
Verified
Review by
LicenceFacts from state statutes; statutory text is government work and the facts in it are not copyrightable (Feist, 1991). Each record quotes a short attributed excerpt and links back to the page it was read from. Citation note, checked 2026-10-14: The Georgia row is cited to codes.findlaw.com rather than to an official state host, because Georgia does not publish its code anywhere a single section can be fetched at a stable URL — Georgia's own free O.C.G.A., which the General Assembly contracts LexisNexis to publish, is a JavaScript application at advance.lexis.com that serves no statutory text to a fetch. That mirror now sits behind a Cloudflare challenge and returns 403 to everyone, an invented-slug control included, so these rows cannot at present be re-checked against the page they cite. The values were read from those pages when the records were harvested and nothing here has changed them; what is missing is any ongoing check that they are still current.

Cite as: Construction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations, referencesource.org/construction-retainage-limits-by-state/, checked 2026-08-16.

Want this list kept current for you?The whole dataset as CSV and JSON, every value with its source and the quote it came from, re-checked and re-sent — $9 a month. What you get, and how to ask for it.

Covers 30 of the 50 states and the District of Columbia: Arizona, California, Colorado, Connecticut, Florida, Georgia, Illinois, Indiana, Iowa, Kentucky, Louisiana, Maryland, Massachusetts, Michigan, Minnesota, Missouri, Nebraska, Nevada, New Mexico, New York, North Carolina, Ohio, Oregon, Pennsylvania, South Carolina, Tennessee, Texas, Virginia, Washington, Wisconsin. A state not named here is one whose own agency page we have not read yet, which is not the same as that state having nothing to state.

The data

StatePublic project retainage cap (%)Private project retainage cap (%)Release deadlineEscrow requiredMilestone reductionStatutory citation
Arizona10%; 5% after the contract is 50% complete; no retention at all for job-order-contracting contractsno statutory cap in Ariz. Rev. Stat. § 32-1182, the prompt-payment section for owners and contractors, which lets the owner withhold "a reasonable amount for retention" and sets no percentage; § 41-2576 governs retention by the statewithin sixty days after final completion and acceptanceno (the contractor may provide substitute security instead, and keeps the interest)at 50% complete, one-half of the amount retained is released and later retention is capped at five per centAriz. Rev. Stat. § 41-2576 (retention by the state); § 32-1182 (progress payments by an owner, read for the private-project field)
California5%5% of each payment, and no more than 5% of the contract price in total, on a private work of improvement under a contract entered into on or after January 1, 2026; not on a residential project that is not mixed-use and does not exceed four stories (Cal. Civ. Code § 8811)upon final completion and acceptance of the project (state public works contracts, Cal. Pub. Cont. Code § 10261)not addressed in this statuteafter 95% of the work has been completed, the department may reduce the funds withheld to an amount not less than 125 percent of the estimated value of the work yet to be completedCal. Pub. Cont. Code § 10261 (state public works contracts); Cal. Civ. Code § 8811 (private works of improvement)
Colorado5%5%not specified in this sectionnot addressed in C.R.S. § 38-46-103noneC.R.S. § 38-46-103
Connecticut7.5% on a state agency contract, reduced to five per cent when fifty per cent of the contract is completed; 2.5% on a Department of Transportation contract; 5% where the awarding authority is a municipalityfive per cent of the estimated amount of a progress payment for the life of the construction projectnot later than thirty days after the issuance of a certificate of final completion by the owner or the owner's authorized representative, or thirty days after the owner's equivalent written acceptance of the work (private work); § 49-41b sets no final-release deadline for public workyes on private work — an escrow account shall be established for all retainage, in a state or national bank or a savings and loan domiciled in this state; § 42-158q keeps that duty off any public building or public work of the state or a municipality, so none on public workon a state agency contract the seven and one-half per cent drops to five per cent when fifty per cent of the contract is completed; none for private workConn. Gen. Stat. §§ 42-158i, 42-158k, 42-158p and 42-158q (private work); § 49-41b (public work)
Florida5%no statutory cap in Fla. Stat. § 715.12, the Construction Contract Prompt Payment Law, under which an owner and a contractor "may agree to a provision that allows the owner to withhold a portion of each progress payment"; § 255.078 caps public construction onlysame time limits for payment of a payment request apply regardless of whether the payment request is for, or includes, retainagenot addressed in Fla. Stat. § 255.078noneFla. Stat. § 255.078 (public construction); Fla. Stat. § 715.12 (Construction Contract Prompt Payment Law, read for the private-project field)
Georgia5%no statutory cap in Ga. Code Ann. § 13-10-80, which governs public works construction contracts only; this record read no private-work statutewithin 30 days after invoice at substantial completionnot addressed in Ga. Code Ann. § 13-10-80noneGa. Code Ann. § 13-10-80 (public works construction contracts)
Illinois10% before 50% complete; 5% after 50% complete10% before 50% complete; 5% after 50% completenot specified in this sectionnot addressed in 815 ILCS 603/20at 50% completion, retainage reduced to no more than 5%815 ILCS 603/20
Indianano statutory cap in Ind. Code § 5-16-5.5-3, which governs a state agency's contract for a public building, work or improvement, applies to contracts that "contain provision for retainage" and sets no percentage; whatever is retained must be placed in an escrow accountno statutory cap in Ind. Code § 5-16-5.5-3, which governs a state agency's contracts for a public building, work or improvement only; this record read no private-work statuteper contract termsyesnoneInd. Code § 5-16-5.5-3 (a state agency's public works contracts)
Iowa3% of each monthly payment (Iowa Code § 573.12(1)(a), as amended by 2025 Acts, ch. 29, § 1); § 573.12(1)(b) caps what a contractor may retain from each payment to a subcontractor at the lesser of three percent or the amount the subcontract specifiesno statutory cap in Iowa Code § 573.12, which governs contracts for public improvements only; this record read no private-work statute30 days after the completion and final acceptance of the improvement, when the unpaid fund is released and paid to the contractor, less a sum equal to double the total amount of any claims on file at the end of that period (Iowa Code § 573.14(1))not addressed in Iowa Code § 573.12 or § 573.14, neither of which says how retained funds are to be held; § 573.12(3)(b) is the nearest provision and is about who gets the interest they earn, not about an escrow accountnoneIowa Code § 573.12 (payments and retention from payments on public improvement contracts), as amended by 2025 Acts, ch. 29, § 1; § 573.14 (retention of unpaid funds, and when they are released)
Kentucky10% until 50% complete, then 5%10% until 50% complete, then 5%30 days after substantial completionnot addressed in KRS 371.410retainage held after fifty-one percent (51%) of the construction project has been completed shall not be more than five percent (5%)KRS 371.410
Louisianaten percent of the contract price on projects of less than five hundred thousand dollars, and five percent of the contract price on projects of five hundred thousand dollars or moreno statutory cap; the Private Works Act governs how private retainage is escrowed and bonded rather than how much may be withheld, and R.S. 9:4858 leaves the amount to the contracton public work, until the expiration of forty-five days after the recordation of formal acceptance of such work, or notice of default by the contractor or subcontractoryes on private work — under R.S. 9:4857 retainage withheld on a private contract of fifty thousand dollars or more shall be deposited into an interest bearing escrow account, and the Section does not reach a single or double family residence or the listed industrial facilities; none on public work, where R.S. 38:2249 instead lets the contractor withdraw the retained amount by depositing security of equal valuenone in this Section; the cap turns on the size of the project rather than on a completion milestoneLa. Rev. Stat. §§ 38:2248 and 38:2249 on public works, and §§ 9:4857 and 9:4858 of the Private Works Act on private works; the public Section may not be waived and does not apply to the Department of Transportation and Development
Maryland5% of the total amount, where the contractor has furnished 100% payment security and 100% performance security (State procurement contracts)5% of the contract price, where the contractor has furnished 100% performance and payment security; the section does not apply to a contract under $100,000within 90 days after the date of substantial completionoptional (public retainage may be deposited in an interest-bearing escrow account, and interest is then paid pro rata)noneMd. Code, Real Prop. § 9-304; Md. Code, State Fin. & Proc. § 13-225
Massachusetts5% of the approved amount of each periodic payment on public building contracts5% of any progress payment, on a contract for construction with an original contract price of not less than $3,000,000, excluding projects of 1 to 4 dwelling unitsnot later than 30 days following submission of the applicationnot addressed in Mass. Gen. Laws ch. 149, § 29F; Mass. Gen. Laws ch. 30, § 39KnoneMass. Gen. Laws ch. 149, § 29F; Mass. Gen. Laws ch. 30, § 39K
MichiganNot more than 10% of the dollar value of all work in place until work is 50% in placeno statutory cap; Act 524 of 1980 reaches only a facility that is paid for with public funds or a special assessmentreleased to a contractor together with the final progress payment, which § 125.1562(3) times at thirty days after the architect or professional engineer certifies the work is in place, or fifteen days after the public agency receives the state or federal funds, whichever is laterpublic only (deposited in an interest bearing account in a regulated financial institution in this state, unless the retained funds are to come from a state or federal grant and have not yet been paid to the public agency)After the work is 50% in place, additional retainage shall not be withheld unless the public agency determines that the contractor is not making satisfactory progressMich. Comp. Laws §§ 125.1561 to 125.1563 (Act 524 of 1980); § 125.1561(c) puts a contract worth less than $30,000.00, or one providing for 3 or fewer payments, outside "construction contract", and § 125.1561(h) puts the state transportation department, a school district, a junior or community college, the Michigan state housing development authority and a municipal electric utility outside "public agency"
Minnesota5%5%60 days after substantial completionnot addressed in Minn. Stat. § 337.10owner may reduce or eliminate retainage if work is progressing satisfactorilyMinn. Stat. § 337.10
Missouri5%10% of each payment due from the owner to the contractor, on private construction projects other than single-family residential construction and other residential construction of four or fewer units; the contract may let the owner retain more if the contractor's performance is not in accordance with the contract (RSMo §§ 436.303 and 436.336)30 days after acceptance and receipt of required documentation (public works, RSMo § 34.057)not addressed in RSMo § 34.057public owner may reduce or eliminate retainage if work is proceeding satisfactorilyRSMo § 34.057 (public works); RSMo §§ 436.303 and 436.336 (private construction work)
Nebraska10% for a political subdivision; the Construction Prompt Pay Act does not reach State of Nebraska contracts10%, and no more than 5% of additional progress payments once the withheld scope is 50% completewithin forty-five days after the project, or a designated portion thereof, is substantially completenot addressed in Neb. Rev. Stat. §§ 45-1202, 45-1203, 45-1204at 50% complete, no more than five percent of any additional progress payment, conditional on assurances of continued performance and financial responsibilityNeb. Rev. Stat. §§ 45-1202, 45-1203, 45-1204
Nevada5%5% of each payment to the prime contractor, where the agreement authorizes the owner to withhold a retention amount; NRS 624.609 does not apply to an agreement with a natural person who owns a single-family residence or to a public work (NRS 624.622)within 30 days after occupancy, use, or recording of notice of completion, whichever occurs first (public works, NRS 338.515)not addressed in NRS 338.515after 50% of the work has been completed, the public body may pay remaining progress payments without withholding additional retainageNRS 338.515 (public works); NRS 624.609 and 624.622 (private works of improvement)
New Mexico0% — the act repeals the retainage provisions of Chapter 57, Article 28 and prohibits the withholding of amounts due for work performed0% — the same prohibition binds a private owner, but the Prompt Payment Act does not apply to construction contracts for residential property containing four or fewer dwelling unitsno retainage may be withheld, so there is nothing to release; an undisputed request for payment must be paid within twenty-one days after the owner receives itno — the act prohibits withholding outright rather than regulating how retainage is heldnone — withholding is prohibited from the first progress paymentNMSA 1978 §§ 57-28-1 to 57-28-11 (Prompt Payment Act), as amended by Laws 2007, ch. 213 (S.B. 604, 2007 Regular Session); § 57-28-2 puts the department of transportation outside the act’s definition of "owner"
New York5% of each progress payment; up to 10% where the public owner does not require both a performance bond and a labor and material bond in the full amount of the contract5%30 days after final approval of the work (private contracts, Gen. Bus. Law § 756-c)not addressed in N.Y. Gen. Bus. Law § 756-c or Gen. Mun. Law § 106-bnoneN.Y. Gen. Mun. Law § 106-b (public work); N.Y. Gen. Bus. Law § 756-c (private contracts)
North Carolina5%no statutory cap in N.C. Gen. Stat. ch. 22C (Payments to Subcontractors), which sets no percentage for an owner and limits what a contractor may withhold from a subcontractor to "a reasonable amount for retainage not to exceed the initial percentage retained by the owner" (§ 22C-4); § 143-134.1 governs public construction contracts only60 days after substantial completion or beneficial occupancynot addressed in N.C. Gen. Stat. § 143-134.1retainage eliminated after 50% complete with surety consentN.C. Gen. Stat. § 143-134.1 (public construction contracts); N.C. Gen. Stat. § 22C-4 (payments to subcontractors, read for the private-project field)
Ohio4% (payments at not less than 96%)no statutory cap in Ohio Rev. Code § 4113.61, the prompt-payment section, under which a contractor may reduce a subcontractor's payment "by any retainage provision contained in the contract"; §§ 153.12 and 153.13 govern public improvements onlywithin thirty days of substantial completion, occupation, use or acceptance of the project; any amount still withheld pending final completion, not later than thirty days after final completionoptional, public work only — money due is paid to the contractor or deposited in an escrow account selected by mutual agreement between the contractor and the public ownernoneOhio Rev. Code §§ 153.12, 153.13 and 153.63 (public improvements); § 4113.61 (prompt payment, read for the private-project field)
Oregon5%5%interest commences 30 days after completion and acceptanceyes (contracts exceeding $500,000)noneORS 701.420
Pennsylvania10% of the amount due the contractor until 50% of the contract is completed, then no more than 5% after that, of the value of completed work based on monthly progress payment requests (62 Pa.C.S. § 3921(a)); a lower limit applies where the Department of General Services is the government agency (§ 3921(b))no statutory percentage cap in the Contractor and Subcontractor Payment Act (73 P.S. § 509), which sets when retainage must be released and no percentage; a contractor may withhold retainage from a subcontractor "in accordance with their agreement"30 days after final acceptance of the work (private work, 73 P.S. § 509, the Contractor and Subcontractor Payment Act)not addressed in 73 P.S. § 509 (Contractor and Subcontractor Payment Act, Section 9)contractor or subcontractor may post a maintenance bond for 120% of retainage upon reaching substantial completion to facilitate release (private work, 73 P.S. § 509)73 P.S. § 509 (Contractor and Subcontractor Payment Act, Section 9 — private work); 62 Pa.C.S. § 3921 (retainage on a government agency's public works contract)
South Carolina3.5% of each progress payment or installment on a contract or subcontract for construction with the State or a general contractor (S.C. Code Ann. § 11-35-3030(4)(a)); Title 29, Chapter 6, whose prompt-payment rules reach a government owner too, sets no percentageno statutory cap in S.C. Code Ann. Title 29, Chapter 6, where § 29-6-40 lets an owner, contractor or subcontractor withhold "a reasonable amount for retainage" and sets no percentage21 days for owner to contractor; 7 days for contractor to subcontractor after receipt (S.C. Code Ann. § 29-6-30, in the prompt-payment chapter, whose "owner" includes a government agency)not addressed in S.C. Code Ann. § 29-6-40noneS.C. Code Ann. § 29-6-40 (prompt payment, whose "owner" includes any state, local, or municipal government agency); S.C. Code Ann. § 11-35-3030(4) (retention on state construction contracts)
Tennessee5%5%90 days after completion of the work or 90 days after substantial completionyesnoneTenn. Code Ann. § 66-34-103
Texas10% (contracts <$5M); 5% (contracts ≥$5M)no statutory cap in Tex. Prop. Code ch. 53, which treats retainage as "the amount specified to be retained in the contract" (§ 53.025) and separately requires the owner to reserve part of the contract price until 30 days after the work is completed (§ 53.101); Gov't Code § 2252.032 governs public works contracts onlyupon completion of the work required to be performed under the contractoptional (contracts ≥$10M, by agreement)noneTex. Gov't Code § 2252.032 (public works contracts); Tex. Prop. Code §§ 53.025 and 53.101 (read for the private-project field)
Virginia5%no statutory cap in Va. Code § 11-4.6, the payment section for construction contracts with an owner other than a public body, one subdivision of which says it does not "apply to or prohibit the inclusion of any retainage provisions in a construction contract"; § 2.2-4333 governs public contracts onlyincluded in the final paymentnot addressed in Va. Code § 2.2-4333noneVa. Code § 2.2-4333 (public contracts); Va. Code § 11-4.6 (construction contracts with a private owner, read for the private-project field)
Washington5%5% of the contract price of the work completed, on private construction projects other than single-family residential construction of less than 12 units (RCW 60.30.010)60 days after completion of all contract work (public improvement contracts, RCW 60.28.011)optionalcontractor may request retainage be reduced to 100% of the value of work remainingRCW 60.28.011 (public improvement contracts); RCW 60.30.010 (private construction projects)
Wisconsin5% until 50% complete; 0% after 50% complete (unless unsatisfactory progress)no statutory cap in Wis. Stat. § 66.0901(9)(b), which governs a municipality's contracts for a public work or building only; this record read no private-work statutenot specified in this section — payment of an amount retained upon substantial completion is permissive, not a deadlinenot addressed in Wis. Stat. § 66.0901(9)(b)at 50% completion, no further retainage withheld (full payments resume)Wis. Stat. § 66.0901(9)(b) (a municipality's public works contracts)

Where this came from

Every record above links the page it was taken from and quotes the sentence that states it. These are the 58 sources this dataset was assembled from.

Machine-readable

From your own code

Same records, same quotes, without scraping the page: refsource is on PyPI and npm. Each value comes back carrying the URL it was read from and the sentence on that page that states it — .source and .quote sit on the value itself rather than in a side channel, so the checking step is available instead of skipped.

pip install refsource
refsource lookup construction-retainage-limits-by-state state=Arizona

npx -y refsource lookup construction-retainage-limits-by-state state=Arizona

Set your AI assistant up to use this

Two files and no account. Put this in .mcp.json at the root of your project — Claude Code, Cursor, Windsurf, VS Code and Codex all read that file — and your assistant can look this dataset up instead of recalling it. The server is remote, keyless and read-only.

{
  "mcpServers": {
    "referencesource": {
      "type": "http",
      "url": "https://referencesource.org/mcp"
    }
  }
}

Add to Cursor · or, on the command line: claude mcp add --transport http referencesource https://referencesource.org/mcp --scope project

Then one line in the project's CLAUDE.md or AGENTS.md, so the assistant knows when to reach for it:

When a question needs "Construction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations", call the referencesource MCP server at https://referencesource.org/mcp (tool `search_records`, dataset_slug `construction-retainage-limits-by-state`) instead of answering from memory — every record it returns carries its source URL and a verbatim quote from that page.

What each tool does, and the servers built over single registers: Connect your AI assistant.

30 records. last verified against source . due for re-check by .

Licence. Facts from state statutes; statutory text is government work and the facts in it are not copyrightable (Feist, 1991). Each record quotes a short attributed excerpt and links back to the page it was read from. Citation note, checked 2026-10-14: The Georgia row is cited to codes.findlaw.com rather than to an official state host, because Georgia does not publish its code anywhere a single section can be fetched at a stable URL — Georgia's own free O.C.G.A., which the General Assembly contracts LexisNexis to publish, is a JavaScript application at advance.lexis.com that serves no statutory text to a fetch. That mirror now sits behind a Cloudflare challenge and returns 403 to everyone, an invented-slug control included, so these rows cannot at present be re-checked against the page they cite. The values were read from those pages when the records were harvested and nothing here has changed them; what is missing is any ongoing check that they are still current.