For Indiana, public project retainage cap (%) is per contract terms (escrow required when withheld); private project retainage cap (%) is no statutory cap; release deadline is per contract terms; escrow required is yes; milestone reduction is none, recorded from its source on 2026-08-17.

State
Indiana verified
Public project retainage cap (%)
per contract terms (escrow required when withheld)
Private project retainage cap (%)
no statutory cap
Release deadline
per contract terms
Escrow required
yes
Milestone reduction
none
Statutory citation
Ind. Code § 5-16-5-5.3 our reading
Sourcecodes.findlaw.com
Verified
Review by
DatasetConstruction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations

Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.

What the source says

provision for retainage shall include in their respective contracts a provision that at the time any retainage is withheld, the state agency and/or contractor shall place such retainage in an escrow account, with a bank, savings and loan institution, or the State of Indiana or an instrumentality thereof, as escrow agent selected by mutual agreement

codes.findlaw.com, retrieved 2026-08-17

Source

Last verified against source: . Due for re-check by . This page as Markdown · OKF bundle · full dataset as JSON.