Georgia
For Georgia, public project retainage cap (%) is 5%; private project retainage cap (%) is no statutory cap in Ga. Code Ann. § 13-10-80, which governs public works construction contracts only; this record read no private-work statute; release deadline is within 30 days after invoice at substantial completion; escrow required is not addressed in Ga. Code Ann. § 13-10-80; milestone reduction is none, recorded from its source on 2026-08-17.
- State
- Georgia our reading
- Public project retainage cap (%)
- 5%
- Private project retainage cap (%)
- no statutory cap in Ga. Code Ann. § 13-10-80, which governs public works construction contracts only; this record read no private-work statute
- Release deadline
- within 30 days after invoice at substantial completion
- Escrow required
- not addressed in Ga. Code Ann. § 13-10-80
- Milestone reduction
- none
- Statutory citation
- Ga. Code Ann. § 13-10-80 (public works construction contracts) our reading
Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.
Cite as: Georgia — Construction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations (Construction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations), referencesource.org/construction-retainage-limits-by-state/georgia/, checked 2026-08-17.
What the source says
Retainage to a maximum of 5 percent of each progress payment. At the discretion of the owner and with the approval of the contractor, the retainage of each subcontractor may be released separately as the subcontractor completes his or her work.
— codes.findlaw.com, retrieved 2026-08-17
Where each value comes from
The value above is stated away from the sentence quoted with the answer, so the passage that states it is shown here too.
Private project retainage cap (%)
(b) In any public works construction contract entered into on or after July 1, 2022, with an owner, as defined in paragraph (3) of subsection (a) of this Code section, such contract shall provide for the following:
— all from codes.findlaw.com, retrieved 2026-08-17
Source
- codes.findlaw.comhttps://codes.findlaw.com/ga/title-13-contracts/ga-code-sect-13-10-80.html
Work out the dollars: how much may be withheld from a payment in Georgia?