Reference Source

Florida

For Florida, public project retainage cap (%) is 5%; private project retainage cap (%) is no statutory cap in Fla. Stat. § 715.12, the Construction Contract Prompt Payment Law, under which an owner and a contractor "may agree to a provision that allows the owner to withhold a portion of each progress payment"; § 255.078 caps public construction only; release deadline is same time limits for payment of a payment request apply regardless of whether the payment request is for, or includes, retainage; escrow required is not addressed in Fla. Stat. § 255.078; milestone reduction is none, recorded from its source on 2026-09-03.

State
Florida our reading
Public project retainage cap (%)
5%
Private project retainage cap (%)
no statutory cap in Fla. Stat. § 715.12, the Construction Contract Prompt Payment Law, under which an owner and a contractor "may agree to a provision that allows the owner to withhold a portion of each progress payment"; § 255.078 caps public construction only
Release deadline
same time limits for payment of a payment request apply regardless of whether the payment request is for, or includes, retainage verified
Escrow required
not addressed in Fla. Stat. § 255.078
Milestone reduction
none
Statutory citation
Fla. Stat. § 255.078 (public construction); Fla. Stat. § 715.12 (Construction Contract Prompt Payment Law, read for the private-project field) our reading
Sourceleg.state.fl.us
Verified
Review by
DatasetConstruction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations

Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.

Cite as: Florida — Construction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations (Construction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations), referencesource.org/construction-retainage-limits-by-state/florida/, checked 2026-09-03.

What the source says

a public entity may withhold from each progress payment made to the contractor an amount not exceeding 5 percent of the payment as retainage.

— leg.state.fl.us, retrieved 2026-09-03

Where each value comes from

These values are stated in different places, and not all on the same page, so each is shown with the passage that states it and the source that passage came from.

Private project retainage cap (%)

An owner and a contractor may agree to a provision that allows the owner to withhold a portion of each progress payment until substantial completion of the entire project.

— from leg.state.fl.us, retrieved 2026-09-03

Release deadline

(4) The same time limits for payment of a payment request apply regardless of whether the payment request is for, or includes, retainage.

— from leg.state.fl.us, retrieved 2026-09-03

Statutory citation

255.078 Public construction retainage.

— from leg.state.fl.us, retrieved 2026-09-03

Sources

Open the page on leg.state.fl.us that states this — the page quoted above, at its publisher. Unpaid: we earn nothing from this link and it is not an advertisement.

Last verified against source: . Due for re-check by . This page as Markdown · OKF bundle · full dataset as JSON.

Want this list kept current for you?The whole dataset as CSV and JSON, every value with its source and the quote it came from, re-checked and re-sent — $9 a month. What you get, and how to ask for it.