For Connecticut, public project retainage cap (%) is 7.5% on a state agency contract, reduced to five per cent when fifty per cent of the contract is completed; 2.5% on a Department of Transportation contract; 5% where the awarding authority is a municipality; private project retainage cap (%) is five per cent of the estimated amount of a progress payment for the life of the construction project; release deadline is not later than thirty days after the issuance of a certificate of final completion by the owner or the owner's authorized representative, or thirty days after the owner's equivalent written acceptance of the work (private work); § 49-41b sets no final-release deadline for public work; escrow required is yes on private work — an escrow account shall be established for all retainage, in a state or national bank or a savings and loan domiciled in this state; § 42-158q keeps that duty off any public building or public work of the state or a municipality, so none on public work; milestone reduction is on a state agency contract the seven and one-half per cent drops to five per cent when fifty per cent of the contract is completed; none for private work, recorded from its source on 2026-10-08.

State
Connecticut our reading
Public project retainage cap (%)
7.5% on a state agency contract, reduced to five per cent when fifty per cent of the contract is completed; 2.5% on a Department of Transportation contract; 5% where the awarding authority is a municipality
Private project retainage cap (%)
five per cent of the estimated amount of a progress payment for the life of the construction project
Release deadline
not later than thirty days after the issuance of a certificate of final completion by the owner or the owner's authorized representative, or thirty days after the owner's equivalent written acceptance of the work (private work); § 49-41b sets no final-release deadline for public work
Escrow required
yes on private work — an escrow account shall be established for all retainage, in a state or national bank or a savings and loan domiciled in this state; § 42-158q keeps that duty off any public building or public work of the state or a municipality, so none on public work
Milestone reduction
on a state agency contract the seven and one-half per cent drops to five per cent when fifty per cent of the contract is completed; none for private work
Statutory citation
Conn. Gen. Stat. §§ 42-158i, 42-158k, 42-158p and 42-158q (private work); § 49-41b (public work) our reading
Sourcecga.ct.gov
Verified
Review by
DatasetConstruction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations

Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.

Cite as: Connecticut — Construction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations (Construction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations), referencesource.org/construction-retainage-limits-by-state/connecticut/, checked 2026-10-08.

What the source says

No construction contract may provide for any retainage in an amount that exceeds five per cent of the estimated amount of a progress payment for the life of the construction project.

— cga.ct.gov, retrieved 2026-10-08

Where each value comes from

These values are stated in different places, and not all on the same page, so each is shown with the passage that states it and the source that passage came from.

Public project retainage cap (%)

(A) the awarding authority shall not withhold more than seven and one-half per cent from any periodic or final payment which is otherwise properly due to the general or prime contractor under the terms of such contract, provided, when fifty per cent of the contract is completed, said amount shall be reduced to five per cent

— from cga.ct.gov, retrieved 2026-10-08

Private project retainage cap (%)

“Construction contract” or “contract” does not include (A) any public works or other building contract entered into with this state, the United States, any other state, and any municipality or other political subdivision of this state or any other state, (B) a contract or project funded or insured by the United States Department of Housing and Urban Development, (C) a contract between an owner and a contractor for an amount of twenty-five thousand dollars or less or a subcontract which results from such a contract, or (D) a contract for a building intended for residential occupancy containing four or less units.

— from cga.ct.gov, retrieved 2026-10-08

Release deadline

All retainage shall be paid by the owner not later than thirty days after the issuance of a certificate of final completion by the owner or the owner's authorized representative or not later than thirty days after the equivalent written acceptance of the construction project work by the owner.

— from cga.ct.gov, retrieved 2026-10-08

Escrow required

An escrow account shall be established for all retainage, subject to the following: (a) An escrow account shall be established in state or national banks domiciled in this state or in savings and loan associations domiciled in this state.

— from cga.ct.gov, retrieved 2026-10-08

Milestone reduction

(B) any such general or prime contractor shall not withhold from any subcontractor more than (i) seven and one-half per cent from any periodic or final payment which is otherwise due to the subcontractor, or (ii) the amount withheld by the awarding authority from such general or prime contractor under subparagraph (A) of this subdivision, whichever is less, provided, when fifty per cent of the contract is completed, said amount shall be reduced to five per cent.

— from cga.ct.gov, retrieved 2026-10-08

Statutory citation

The provisions of section 42-158p do not apply to construction contracts for residential property containing four or fewer dwelling units or to construction contracts of less than twenty-five thousand dollars total value or to construction contracts relating to any public building or public work of the state or a municipality or other political subdivision of the state.

— from cga.ct.gov, retrieved 2026-10-08

Sources

Open the page on cga.ct.gov that states this — the page quoted above, at its publisher. Unpaid: we earn nothing from this link and it is not an advertisement.

Last verified against source: . Due for re-check by . This page as Markdown · OKF bundle · full dataset as JSON.

Want this list kept current for you?The whole dataset as CSV and JSON, every value with its source and the quote it came from, re-checked and re-sent — $9 a month. What you get, and how to ask for it.