Colorado
For Colorado, public project retainage cap (%) is 5%; private project retainage cap (%) is 5%; release deadline is not specified in this section; escrow required is not addressed in C.R.S. § 38-46-103; milestone reduction is none, recorded from its source on 2026-08-17.
- State
- Colorado our reading
- Public project retainage cap (%)
- 5%
- Private project retainage cap (%)
- 5%
- Release deadline
- not specified in this section
- Escrow required
- not addressed in C.R.S. § 38-46-103
- Milestone reduction
- none
- Statutory citation
- C.R.S. § 38-46-103 our reading
Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.
Cite as: Colorado — Construction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations (Construction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations), referencesource.org/construction-retainage-limits-by-state/colorado/, checked 2026-08-17.
What the source says
A property owner, contractor, or subcontractor shall not withhold as retainage more than five percent of the price of the work completed under the contract or subcontract.
— colorado.public.law, retrieved 2026-08-17
Where each value comes from
The value above is stated away from the sentence quoted with the answer, so the passage that states it is shown here too.
Statutory citation
C.R.S. Section 38-46-103 Private construction contracts retainage conditions precedent
— all from colorado.public.law, retrieved 2026-08-17
Source
- colorado.public.lawhttps://colorado.public.law/statutes/crs_38-46-103
Work out the dollars: how much may be withheld from a payment in Colorado?