California
For California, public project retainage cap (%) is 5%; private project retainage cap (%) is 5% of each payment, and no more than 5% of the contract price in total, on a private work of improvement under a contract entered into on or after January 1, 2026; not on a residential project that is not mixed-use and does not exceed four stories (Cal. Civ. Code § 8811); release deadline is upon final completion and acceptance of the project (state public works contracts, Cal. Pub. Cont. Code § 10261); escrow required is not addressed in this statute; milestone reduction is after 95% of the work has been completed, the department may reduce the funds withheld to an amount not less than 125 percent of the estimated value of the work yet to be completed, recorded from its source on 2026-09-03.
- State
- California our reading
- Public project retainage cap (%)
- 5%
- Private project retainage cap (%)
- 5% of each payment, and no more than 5% of the contract price in total, on a private work of improvement under a contract entered into on or after January 1, 2026; not on a residential project that is not mixed-use and does not exceed four stories (Cal. Civ. Code § 8811)
- Release deadline
- upon final completion and acceptance of the project (state public works contracts, Cal. Pub. Cont. Code § 10261)
- Escrow required
- not addressed in this statute
- Milestone reduction
- after 95% of the work has been completed, the department may reduce the funds withheld to an amount not less than 125 percent of the estimated value of the work yet to be completed
- Statutory citation
- Cal. Pub. Cont. Code § 10261 (state public works contracts); Cal. Civ. Code § 8811 (private works of improvement) our reading
Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.
Cite as: California — Construction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations (Construction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations), referencesource.org/construction-retainage-limits-by-state/california/, checked 2026-09-03.
What the source says
The department shall withhold not more than 5 percent of the contract price until final completion and acceptance of the project. However, at any time after 95 percent of the work has been completed, the department may reduce the funds withheld to an amount not less than 125 percent of the estimated value of the work yet to be completed
— leginfo.legislature.ca.gov, retrieved 2026-09-03
Where each value comes from
These values are stated in different places, and not all on the same page, so each is shown with the passage that states it and the source that passage came from.
Private project retainage cap (%)
A retention payment withheld from a payment by an owner from the direct contractor, by the direct contractor from any subcontractor, and by a subcontractor from any subcontractor thereunder, for a private work of improvement, shall not exceed 5 percent of the payment.
— from california.public.law, retrieved 2026-09-03
Statutory citation
10261. (a) Payments upon contracts shall be made as the department prescribes upon estimates made and approved by the department
— from leginfo.legislature.ca.gov, retrieved 2026-09-03
Sources
- leginfo.legislature.ca.govhttps://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?sectionNum=10261.&lawCode=PCC
- california.public.lawhttps://california.public.law/codes/civil_code_section_8811
Work out the dollars: how much may be withheld from a payment in California?