Arizona

For Arizona, public project retainage cap (%) is 10%; 5% after the contract is 50% complete; no retention at all for job-order-contracting contracts; private project retainage cap (%) is no statutory cap in Ariz. Rev. Stat. § 32-1182, the prompt-payment section for owners and contractors, which lets the owner withhold "a reasonable amount for retention" and sets no percentage; § 41-2576 governs retention by the state; release deadline is within sixty days after final completion and acceptance; escrow required is no (the contractor may provide substitute security instead, and keeps the interest); milestone reduction is at 50% complete, one-half of the amount retained is released and later retention is capped at five per cent, recorded from its source on 2026-10-08.

State
Arizona our reading
Public project retainage cap (%)
10%; 5% after the contract is 50% complete; no retention at all for job-order-contracting contracts
Private project retainage cap (%)
no statutory cap in Ariz. Rev. Stat. § 32-1182, the prompt-payment section for owners and contractors, which lets the owner withhold "a reasonable amount for retention" and sets no percentage; § 41-2576 governs retention by the state
Release deadline
within sixty days after final completion and acceptance verified
Escrow required
no (the contractor may provide substitute security instead, and keeps the interest)
Milestone reduction
at 50% complete, one-half of the amount retained is released and later retention is capped at five per cent
Statutory citation
Ariz. Rev. Stat. § 41-2576 (retention by the state); § 32-1182 (progress payments by an owner, read for the private-project field) our reading
Sourceazleg.gov
Verified
Review by
DatasetConstruction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations

Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.

Cite as: Arizona — Construction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations (Construction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations), referencesource.org/construction-retainage-limits-by-state/arizona/, checked 2026-10-08.

What the source says

A. Ten per cent of all construction contract payments shall be retained by this state as insurance of proper performance of the contract or, at the option of the contractor, a substitute security may be provided by the contractor in an authorized form pursuant to rules adopted by the director.

— azleg.gov, retrieved 2026-10-08

Where each value comes from

These values are stated in different places, and not all on the same page, so each is shown with the passage that states it and the source that passage came from.

Public project retainage cap (%)

1. There shall be no retention for job-order-contracting construction services contracts and the purchasing agency may elect to have no retention for construction-manager-at-risk and design-build construction services contracts.

— from azleg.gov, retrieved 2026-10-08

Private project retainage cap (%)

The owner may withhold from a progress payment a reasonable amount for retention.

— from azleg.gov, retrieved 2026-10-08

Release deadline

Any retention shall be paid or substitute security shall be returned to the contractor within sixty days after final completion and acceptance of work under the contract.

— from azleg.gov, retrieved 2026-10-08

Milestone reduction

When the contract is fifty per cent completed, one-half of the amount retained or securities substituted pursuant to this section shall be paid to the contractor upon the contractor's request provided the contractor is making satisfactory progress on the contract and there is no specific cause or claim requiring a greater amount to be retained.

— from azleg.gov, retrieved 2026-10-08

Statutory citation

41-2576. Contract payment retention; partial payment

— from azleg.gov, retrieved 2026-10-08

Sources

Open the page on azleg.gov that states this — the page quoted above, at its publisher. Unpaid: we earn nothing from this link and it is not an advertisement.