# Arizona โ€” Construction retainage limits by US state โ€” maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations For Arizona, public project retainage cap (%) is 10% before 50% complete; 5% after 50% complete; private project retainage cap (%) is no statutory cap in this section; release deadline is within 60 days after final completion and acceptance; escrow required is no (substitute security option available); milestone reduction is at 50% completion, half of retained amount returned and rate drops to 5%, recorded from its source on 2026-08-17. - **State:** Arizona - **Public project retainage cap (%):** 10% before 50% complete; 5% after 50% complete - **Private project retainage cap (%):** no statutory cap in this section - **Release deadline:** within 60 days after final completion and acceptance - **Escrow required:** no (substitute security option available) - **Milestone reduction:** at 50% completion, half of retained amount returned and rate drops to 5% - **Statutory citation:** Ariz. Rev. Stat. ยง 41-2576 _(our reading, not quoted from the source)_ ## What the source says > Ten per cent of all construction contract payments shall be retained by this state as insurance of proper performance of the contract or, at the option of the contractor, a substitute security may be provided by the contractor in an authorized form pursuant to rules adopted by the director. ## Source - https://codes.findlaw.com/az/title-41-state-government/az-rev-st-sect-41-2576.html Last verified: 2026-08-17. Review by: 2027-08-17. Part of [Construction retainage limits by US state โ€” maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations](https://referencesource.org/construction-retainage-limits-by-state/).