Ohio

For Ohio, public project retainage cap (%) is 4% (payments at not less than 96%); private project retainage cap (%) is no statutory cap in Ohio Rev. Code § 4113.61, the prompt-payment section, under which a contractor may reduce a subcontractor's payment "by any retainage provision contained in the contract"; §§ 153.12 and 153.13 govern public improvements only; release deadline is within thirty days of substantial completion, occupation, use or acceptance of the project; any amount still withheld pending final completion, not later than thirty days after final completion; escrow required is optional, public work only — money due is paid to the contractor or deposited in an escrow account selected by mutual agreement between the contractor and the public owner; milestone reduction is none, recorded from its source on 2026-09-03.

State
Ohio our reading
Public project retainage cap (%)
4% (payments at not less than 96%)
Private project retainage cap (%)
no statutory cap in Ohio Rev. Code § 4113.61, the prompt-payment section, under which a contractor may reduce a subcontractor's payment "by any retainage provision contained in the contract"; §§ 153.12 and 153.13 govern public improvements only
Release deadline
within thirty days of substantial completion, occupation, use or acceptance of the project; any amount still withheld pending final completion, not later than thirty days after final completion
Escrow required
optional, public work only — money due is paid to the contractor or deposited in an escrow account selected by mutual agreement between the contractor and the public owner
Milestone reduction
none
Statutory citation
Ohio Rev. Code §§ 153.12, 153.13 and 153.63 (public improvements); § 4113.61 (prompt payment, read for the private-project field) our reading
Sourcecodes.ohio.gov
Verified
Review by
DatasetConstruction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations

Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.

Cite as: Ohio — Construction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations (Construction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations), referencesource.org/construction-retainage-limits-by-state/ohio/, checked 2026-09-03.

What the source says

Partial payments to the contractor for labor performed under either a unit or lump sum price contract shall be made at a rate of not less than ninety-six per cent of the estimates prepared by the contractor and approved by the architect or engineer.

— codes.ohio.gov, retrieved 2026-09-03

Where each value comes from

These values are stated in different places, and not all on the same page, so each is shown with the passage that states it and the source that passage came from.

Private project retainage cap (%)

The contractor may reduce the amount paid by any retainage provision contained in the contract, invoice, or purchase order between the contractor and the subcontractor or material supplier, and may withhold amounts that may be necessary to resolve disputed liens or claims involving the work or labor performed or material furnished by the subcontractor or material supplier.

— from codes.ohio.gov, retrieved 2026-09-03

Release deadline

the retained percentages held in connection with such portion and interest thereon accrued shall, within thirty days of substantial completion of, occupation of, use of, or acceptance of the project, be paid to the primary contractor, withholding only that amount reasonably necessary to assure final completion of the project. Any retained funds withheld after substantial completion of, occupation of, use of, or acceptance of the project, and pending final completion of the project, and interest thereon accrued shall be paid to the primary contractor not later than thirty days after the date of final completion of the project.

— from codes.ohio.gov, retrieved 2026-09-03

Escrow required

shall, on the day it is due, be paid to the contractor or deposited in an escrow account, whichever is applicable, with one or more banks or building and loan associations in the state selected by mutual agreement between the contractor and the public owner.

— from codes.ohio.gov, retrieved 2026-09-03

Sources

Open the page on codes.ohio.gov that states this — the page quoted above, at its publisher. Unpaid: we earn nothing from this link and it is not an advertisement.

Last verified against source: . Due for re-check by . This page as Markdown · OKF bundle · full dataset as JSON.