North Carolina
For North Carolina, public project retainage cap (%) is 5%; private project retainage cap (%) is no statutory cap in N.C. Gen. Stat. ch. 22C (Payments to Subcontractors), which sets no percentage for an owner and limits what a contractor may withhold from a subcontractor to "a reasonable amount for retainage not to exceed the initial percentage retained by the owner" (§ 22C-4); § 143-134.1 governs public construction contracts only; release deadline is 60 days after substantial completion or beneficial occupancy; escrow required is not addressed in N.C. Gen. Stat. § 143-134.1; milestone reduction is retainage eliminated after 50% complete with surety consent, recorded from its source on 2026-09-03.
- State
- North Carolina our reading
- Public project retainage cap (%)
- 5% verified
- Private project retainage cap (%)
- no statutory cap in N.C. Gen. Stat. ch. 22C (Payments to Subcontractors), which sets no percentage for an owner and limits what a contractor may withhold from a subcontractor to "a reasonable amount for retainage not to exceed the initial percentage retained by the owner" (§ 22C-4); § 143-134.1 governs public construction contracts only
- Release deadline
- 60 days after substantial completion or beneficial occupancy
- Escrow required
- not addressed in N.C. Gen. Stat. § 143-134.1
- Milestone reduction
- retainage eliminated after 50% complete with surety consent
- Statutory citation
- N.C. Gen. Stat. § 143-134.1 (public construction contracts); N.C. Gen. Stat. § 22C-4 (payments to subcontractors, read for the private-project field) our reading
Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.
Cite as: North Carolina — Construction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations (Construction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations), referencesource.org/construction-retainage-limits-by-state/north-carolina/, checked 2026-09-03.
What the source says
The owner shall not retain more than five percent (5%) of any periodic payment due a prime contractor.
— ncleg.gov, retrieved 2026-09-03
Where each value comes from
These values are stated in different places, and not all on the same page, so each is shown with the passage that states it and the source that passage came from.
Private project retainage cap (%)
Nothing in this Chapter shall prevent the contractor, at the time of application and certification to the owner, from withholding such application and certification to the owner for payment to the subcontractor for: unsatisfactory job progress; defective construction not remedied; disputed work; third party claims filed or reasonable evidence that claim will be filed; failure of subcontractor to make timely payments for labor, equipment, and materials; damage to contractor or another subcontractor; reasonable evidence that subcontract cannot be completed for the unpaid balance of the subcontract sum; or a reasonable amount for retainage not to exceed the initial percentage retained by the owner.
— from ncleg.gov, retrieved 2026-09-03
Statutory citation
§ 143-134.1. Interest on final payments due to prime contractors; payments to subcontractors.
— from ncleg.gov, retrieved 2026-09-03
Sources
- ncleg.govhttps://www.ncleg.gov/EnactedLegislation/Statutes/HTML/BySection/Chapter_143/GS_143-134.1.html
- ncleg.govhttps://www.ncleg.gov/EnactedLegislation/Statutes/HTML/ByChapter/Chapter_22C.html
Open the page on ncleg.gov that states this — the page quoted above, at its publisher. Unpaid: we earn nothing from this link and it is not an advertisement.
Work out the dollars: how much may be withheld from a payment in North Carolina?