New York
For New York, public project retainage cap (%) is 5% of each progress payment; up to 10% where the public owner does not require both a performance bond and a labor and material bond in the full amount of the contract; private project retainage cap (%) is 5%; release deadline is 30 days after final approval of the work (private contracts, Gen. Bus. Law § 756-c); escrow required is not addressed in N.Y. Gen. Bus. Law § 756-c or Gen. Mun. Law § 106-b; milestone reduction is none, recorded from its source on 2026-08-17.
- State
- New York our reading
- Public project retainage cap (%)
- 5% of each progress payment; up to 10% where the public owner does not require both a performance bond and a labor and material bond in the full amount of the contract
- Private project retainage cap (%)
- 5%
- Release deadline
- 30 days after final approval of the work (private contracts, Gen. Bus. Law § 756-c)
- Escrow required
- not addressed in N.Y. Gen. Bus. Law § 756-c or Gen. Mun. Law § 106-b
- Milestone reduction
- none
- Statutory citation
- N.Y. Gen. Mun. Law § 106-b (public work); N.Y. Gen. Bus. Law § 756-c (private contracts) our reading
Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.
Cite as: New York — Construction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations (Construction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations), referencesource.org/construction-retainage-limits-by-state/new-york/, checked 2026-08-17.
What the source says
By mutual agreement of the relevant parties an owner may retain no more than five per centum of the contract sum as retainage. A contractor or subcontractor may also retain no more than five per centum for retainage and in no case shall retainage exceed the actual percentage retained by the owner. Retainage shall be released by the owner to the contractor no later than thirty days after the final approval of the work under a construction contract.
— newyork.public.law, retrieved 2026-08-17
Where each value comes from
These values are stated in different places, and not all on the same page, so each is shown with the passage that states it and the source that passage came from.
Public project retainage cap (%)
The public owner shall retain not more than five per centum of each progress payment to the contractor except that the public owner may retain in excess of five per centum but not more than ten per centum of each progress payment to the contractor provided that there are no requirements by the public owner for the contractor to provide a performance bond and a labor and material bond both in the full amount of the contract.
— from newyork.public.law, retrieved 2026-08-17
Release deadline
Retainage shall be released by the owner to the contractor no later than thirty days after the final approval of the work under a construction contract.
— from newyork.public.law, retrieved 2026-08-17
Sources
- newyork.public.lawhttps://newyork.public.law/laws/n.y._general_business_law_section_756-c
- newyork.public.lawhttps://newyork.public.law/laws/n.y._general_municipal_law_section_106-b
Open the page on newyork.public.law that states this — the page quoted above, at its publisher. Unpaid: we earn nothing from this link and it is not an advertisement.
Work out the dollars: how much may be withheld from a payment in New York?