For New Mexico, public project retainage cap (%) is 0% — the act repeals the retainage provisions of Chapter 57, Article 28 and prohibits the withholding of amounts due for work performed; private project retainage cap (%) is 0% — the same prohibition binds a private owner, but the Prompt Payment Act does not apply to construction contracts for residential property containing four or fewer dwelling units; release deadline is no retainage may be withheld, so there is nothing to release; an undisputed request for payment must be paid within twenty-one days after the owner receives it; escrow required is no — the act prohibits withholding outright rather than regulating how retainage is held; milestone reduction is none — withholding is prohibited from the first progress payment, recorded from its source on 2026-10-08.

State
New Mexico our reading
Public project retainage cap (%)
0% — the act repeals the retainage provisions of Chapter 57, Article 28 and prohibits the withholding of amounts due for work performed
Private project retainage cap (%)
0% — the same prohibition binds a private owner, but the Prompt Payment Act does not apply to construction contracts for residential property containing four or fewer dwelling units
Release deadline
no retainage may be withheld, so there is nothing to release; an undisputed request for payment must be paid within twenty-one days after the owner receives it
Escrow required
no — the act prohibits withholding outright rather than regulating how retainage is held
Milestone reduction
none — withholding is prohibited from the first progress payment
Statutory citation
NMSA 1978 §§ 57-28-1 to 57-28-11 (Prompt Payment Act), as amended by Laws 2007, ch. 213 (S.B. 604, 2007 Regular Session); § 57-28-2 puts the department of transportation outside the act’s definition of "owner" our reading
Sourcenmlegis.gov
Verified
Review by
DatasetConstruction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations

Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.

Cite as: New Mexico — Construction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations (Construction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations), referencesource.org/construction-retainage-limits-by-state/new-mexico/, checked 2026-10-08.

What the source says

RELATING TO TRADE PRACTICES; CHANGING THE NAME OF THE RETAINAGE ACT TO THE PROMPT PAYMENT ACT; ELIMINATING PROVISIONS OF CHAPTER 57, ARTICLE 28 NMSA 1978 CONCERNING RETAINAGE; PROHIBITING THE WITHHOLDING OF AMOUNTS DUE FOR WORK PERFORMED; AMENDING AND REPEALING SECTIONS OF THE NMSA 1978.

— nmlegis.gov, retrieved 2026-10-08

Where each value comes from

This source states these in separate places, so each value is shown with the passage that states it.

Public project retainage cap (%)

Section 6. REPEAL.--Sections 57-28-4, 57-28-6, 57-28-9 and 57-28-10 NMSA 1978 (being Laws 2001, Chapter 68, Sections 4, 6, 9 and 10) are repealed.

Private project retainage cap (%)

"57-28-3. APPLICABILITY OF ACT.--The provisions of the Prompt Payment Act do not apply to construction contracts for residential property containing four or fewer dwelling units."

Release deadline

A. Except as provided in Subsection B of this section, all construction contracts shall provide that payment for amounts due shall be paid within twenty-one days after the owner receives an undisputed request for payment.

— all from nmlegis.gov, retrieved 2026-10-08

Sources

Open the page on nmlegis.gov that states this — the page quoted above, at its publisher. Unpaid: we earn nothing from this link and it is not an advertisement.

Last verified against source: . Due for re-check by . This page as Markdown · OKF bundle · full dataset as JSON.

Want this list kept current for you?The whole dataset as CSV and JSON, every value with its source and the quote it came from, re-checked and re-sent — $9 a month. What you get, and how to ask for it.