Nevada

For Nevada, public project retainage cap (%) is 5%; private project retainage cap (%) is 5% of each payment to the prime contractor, where the agreement authorizes the owner to withhold a retention amount; NRS 624.609 does not apply to an agreement with a natural person who owns a single-family residence or to a public work (NRS 624.622); release deadline is within 30 days after occupancy, use, or recording of notice of completion, whichever occurs first (public works, NRS 338.515); escrow required is not addressed in NRS 338.515; milestone reduction is after 50% of the work has been completed, the public body may pay remaining progress payments without withholding additional retainage, recorded from its source on 2026-09-03.

State
Nevada our reading
Public project retainage cap (%)
5%
Private project retainage cap (%)
5% of each payment to the prime contractor, where the agreement authorizes the owner to withhold a retention amount; NRS 624.609 does not apply to an agreement with a natural person who owns a single-family residence or to a public work (NRS 624.622)
Release deadline
within 30 days after occupancy, use, or recording of notice of completion, whichever occurs first (public works, NRS 338.515)
Escrow required
not addressed in NRS 338.515
Milestone reduction
after 50% of the work has been completed, the public body may pay remaining progress payments without withholding additional retainage
Statutory citation
NRS 338.515 (public works); NRS 624.609 and 624.622 (private works of improvement) our reading
Sourceleg.state.nv.us
Verified
Review by
DatasetConstruction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations

Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.

Cite as: Nevada — Construction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations (Construction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations), referencesource.org/construction-retainage-limits-by-state/nevada/, checked 2026-09-03.

What the source says

Ninety-five percent of the amount of any progress payment must be paid and 5 percent withheld as retainage until 50 percent of the work required by the contract has been performed.

— leg.state.nv.us, retrieved 2026-09-03

Where each value comes from

These values are stated in different places, and not all on the same page, so each is shown with the passage that states it and the source that passage came from.

Private project retainage cap (%)

(1) A retention amount that, if the owner is authorized to withhold a retention amount pursuant to the agreement, must not exceed 5 percent of the amount of the payment to be made;

— from leg.state.nv.us, retrieved 2026-09-03

Statutory citation

NRS 338.515 Time for making payments; amounts paid; amounts withheld as retainage; rate of interest paid on amounts withheld; powers of Labor Commissioner when worker is owed wages.

— from leg.state.nv.us, retrieved 2026-09-03

Sources

Open the page on leg.state.nv.us that states this — the page quoted above, at its publisher. Unpaid: we earn nothing from this link and it is not an advertisement.

Last verified against source: . Due for re-check by . This page as Markdown · OKF bundle · full dataset as JSON.

Want this list kept current for you?The whole dataset as CSV and JSON, every value with its source and the quote it came from, re-checked and re-sent — $9 a month. What you get, and how to ask for it.