Maryland

For Maryland, public project retainage cap (%) is 5% of the total amount, where the contractor has furnished 100% payment security and 100% performance security (State procurement contracts); private project retainage cap (%) is 5% of the contract price, where the contractor has furnished 100% performance and payment security; the section does not apply to a contract under $100,000; release deadline is within 90 days after the date of substantial completion; escrow required is optional (public retainage may be deposited in an interest-bearing escrow account, and interest is then paid pro rata); milestone reduction is none, recorded from its source on 2026-10-08.

State
Maryland our reading
Public project retainage cap (%)
5% of the total amount, where the contractor has furnished 100% payment security and 100% performance security (State procurement contracts)
Private project retainage cap (%)
5% of the contract price, where the contractor has furnished 100% performance and payment security; the section does not apply to a contract under $100,000
Release deadline
within 90 days after the date of substantial completion verified
Escrow required
optional (public retainage may be deposited in an interest-bearing escrow account, and interest is then paid pro rata)
Milestone reduction
none
Statutory citation
Md. Code, Real Prop. § 9-304; Md. Code, State Fin. & Proc. § 13-225 our reading
Sourcemgaleg.maryland.gov
Verified
Review by
DatasetConstruction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations

Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.

Cite as: Maryland — Construction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations (Construction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations), referencesource.org/construction-retainage-limits-by-state/maryland/, checked 2026-10-08.

What the source says

(e) Undisputed retention proceeds retained by an owner under this section shall be paid within 90 days after the date of substantial completion, as defined by the applicable contract or subcontract.

— mgaleg.maryland.gov, retrieved 2026-10-08

Where each value comes from

These values are stated in different places, and not all on the same page, so each is shown with the passage that states it and the source that passage came from.

Public project retainage cap (%)

(b) (1) If a contractor has furnished 100% payment security and 100% performance security in accordance with Title 17, Subtitle 1 of this article under a State procurement contract for construction, the percentage specified in the contract for retainage may not exceed 5% of the total amount.

— from mgaleg.maryland.gov, retrieved 2026-10-08

Private project retainage cap (%)

(b) This section does not apply to: (1) A contract in an amount less than $100,000; or (2) A contract or subcontract for a project funded wholly or in part by or through the Department of Housing and Community Development. (c) Except as provided in this section: (1) If a contractor has furnished 100% security to guarantee the performance of a contract and 100% security to guarantee payment for labor and materials, including leased equipment: (i) The retention proceeds under the terms of a contract may not exceed 5% of the contract price; and

— from mgaleg.maryland.gov, retrieved 2026-10-08

Escrow required

(3) Retainage withheld by a primary procurement unit and the Maryland Transportation Authority may be deposited in an interest-bearing escrow account in accordance with § 15-108 of this article.

— from mgaleg.maryland.gov, retrieved 2026-10-08