Reference Source

Massachusetts

For Massachusetts, public project retainage cap (%) is 5% of the approved amount of each periodic payment on public building contracts; private project retainage cap (%) is 5% of any progress payment, on a contract for construction with an original contract price of not less than $3,000,000, excluding projects of 1 to 4 dwelling units; release deadline is not later than 30 days following submission of the application; escrow required is not addressed in Mass. Gen. Laws ch. 149, § 29F; Mass. Gen. Laws ch. 30, § 39K; milestone reduction is none, recorded from its source on 2026-10-08.

State
Massachusetts our reading
Public project retainage cap (%)
5% of the approved amount of each periodic payment on public building contracts
Private project retainage cap (%)
5% of any progress payment, on a contract for construction with an original contract price of not less than $3,000,000, excluding projects of 1 to 4 dwelling units
Release deadline
not later than 30 days following submission of the application verified
Escrow required
not addressed in Mass. Gen. Laws ch. 149, § 29F; Mass. Gen. Laws ch. 30, § 39K
Milestone reduction
none
Statutory citation
Mass. Gen. Laws ch. 149, § 29F; Mass. Gen. Laws ch. 30, § 39K our reading
Sourcemalegislature.gov
Verified
Review by
DatasetConstruction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations

Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.

Cite as: Massachusetts — Construction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations (Construction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations), referencesource.org/construction-retainage-limits-by-state/massachusetts/, checked 2026-10-08.

What the source says

(b) No contract for construction shall include retainage that exceeds 5 per cent of any progress payment.

— malegislature.gov, retrieved 2026-10-08

Where each value comes from

These values are stated in different places, and not all on the same page, so each is shown with the passage that states it and the source that passage came from.

Public project retainage cap (%)

the awarding authority will make a periodic payment to the contractor for the work performed during the preceding month and for the materials not incorporated in the work but delivered and suitably stored at the site (or at some location agreed upon in writing) to which the contractor has title or to which a subcontractor has title and has authorized the contractor to transfer title to the awarding authority, upon certification by the contractor that he is the lawful owner and that the materials are free from all encumbrances, but less (1) a retention based on its estimate of the fair value of its claims against the contractor and less (2) a retention for direct payments to subcontractors based on demands for same in accordance with the provisions of section thirty-nine F, and less (3) a retention not exceeding five per cent of the approved amount of the periodic payment.

— from malegislature.gov, retrieved 2026-10-08

Private project retainage cap (%)

''Contract for construction'', a contract for which a lien may be established under sections 2 or 4 of chapter 254 on a project for which the person whose contract with the project owner has an original contract price of not less than $3,000,000; provided, however, that ''contract for construction'' shall not include a project containing or designed to contain at least 1 but not more than 4 dwelling units.

— from malegislature.gov, retrieved 2026-10-08

Release deadline

Subject to subsection (g), an application for payment of retainage shall be paid not later than 30 days following submission of the application; provided, however, that the time period for payment of an application for retainage by the person at each tier of contract below the owner of the project may be extended by 7 days longer than the time period applicable to the person at the tier of contract above the person.

— from malegislature.gov, retrieved 2026-10-08

Sources

Open the page on malegislature.gov that states this — the page quoted above, at its publisher. Unpaid: we earn nothing from this link and it is not an advertisement.

Last verified against source: . Due for re-check by . This page as Markdown · OKF bundle · full dataset as JSON.

Want this list kept current for you?The whole dataset as CSV and JSON, every value with its source and the quote it came from, re-checked and re-sent — $9 a month. What you get, and how to ask for it.