Reference Source

Pennsylvania

For Pennsylvania, public project retainage cap (%) is 10% of the amount due the contractor until 50% of the contract is completed, then no more than 5% after that, of the value of completed work based on monthly progress payment requests (62 Pa.C.S. § 3921(a)); a lower limit applies where the Department of General Services is the government agency (§ 3921(b)); private project retainage cap (%) is no statutory percentage cap in the Contractor and Subcontractor Payment Act (73 P.S. § 509), which sets when retainage must be released and no percentage; a contractor may withhold retainage from a subcontractor "in accordance with their agreement"; release deadline is 30 days after final acceptance of the work (private work, 73 P.S. § 509, the Contractor and Subcontractor Payment Act); escrow required is not addressed in 73 P.S. § 509 (Contractor and Subcontractor Payment Act, Section 9); milestone reduction is contractor or subcontractor may post a maintenance bond for 120% of retainage upon reaching substantial completion to facilitate release (private work, 73 P.S. § 509), recorded from its source on 2026-09-03.

State
Pennsylvania our reading
Public project retainage cap (%)
10% of the amount due the contractor until 50% of the contract is completed, then no more than 5% after that, of the value of completed work based on monthly progress payment requests (62 Pa.C.S. § 3921(a)); a lower limit applies where the Department of General Services is the government agency (§ 3921(b))
Private project retainage cap (%)
no statutory percentage cap in the Contractor and Subcontractor Payment Act (73 P.S. § 509), which sets when retainage must be released and no percentage; a contractor may withhold retainage from a subcontractor "in accordance with their agreement"
Release deadline
30 days after final acceptance of the work (private work, 73 P.S. § 509, the Contractor and Subcontractor Payment Act)
Escrow required
not addressed in 73 P.S. § 509 (Contractor and Subcontractor Payment Act, Section 9)
Milestone reduction
contractor or subcontractor may post a maintenance bond for 120% of retainage upon reaching substantial completion to facilitate release (private work, 73 P.S. § 509)
Statutory citation
73 P.S. § 509 (Contractor and Subcontractor Payment Act, Section 9 — private work); 62 Pa.C.S. § 3921 (retainage on a government agency's public works contract) our reading
Sourcelegis.state.pa.us
Verified
Review by
DatasetConstruction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations

Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.

Cite as: Pennsylvania — Construction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations (Construction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations), referencesource.org/construction-retainage-limits-by-state/pennsylvania/, checked 2026-09-03.

What the source says

If payments under a construction contract are subject to retainage, any amounts which have been retained during the performance of the contract and which are due to be released to the contractor upon final completion shall be paid within 30 days after final acceptance of the work.

— legis.state.pa.us, retrieved 2026-09-03

Where each value comes from

These values are stated in different places, and not all on the same page, so each is shown with the passage that states it and the source that passage came from.

Public project retainage cap (%)

A contract may include a provision for the retainage of a portion of the amount due the contractor to insure the proper performance of the contract except that the sum withheld by the government agency from the contractor shall not exceed 10% of the amount due the contractor until 50% of the contract is completed. When the contract is 50% completed, one-half of the amount retained by the government agency shall be returned to the contractor. However, the architect or engineer must approve the application for payment. The contractor must be making satisfactory progress, and there must be no specific cause for greater withholding. The sum withheld by the government agency from the contractor after the contract is 50% completed shall not exceed 5% of the value of completed work based on monthly progress payment requests.

— from palegis.us, retrieved 2026-09-03

Private project retainage cap (%)

If an owner is not withholding retainage, a contractor may withhold retainage from a subcontractor in accordance with their agreement.

— from legis.state.pa.us, retrieved 2026-09-03

Sources

Last verified against source: . Due for re-check by . This page as Markdown · OKF bundle · full dataset as JSON.

Want this list kept current for you?The whole dataset as CSV and JSON, every value with its source and the quote it came from, re-checked and re-sent — $9 a month. What you get, and how to ask for it.