Tennessee

For Tennessee, public project retainage cap (%) is 5%; private project retainage cap (%) is 5%; release deadline is 90 days after completion of the work or 90 days after substantial completion; escrow required is yes; milestone reduction is none, recorded from its source on 2026-08-16.

State
Tennessee our reading
Public project retainage cap (%)
5% verified
Private project retainage cap (%)
5% verified
Release deadline
90 days after completion of the work or 90 days after substantial completion
Escrow required
yes
Milestone reduction
none
Statutory citation
Tenn. Code Ann. § 66-34-103 our reading
Sourcelaw.justia.com
Verified
Review by
DatasetConstruction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations

Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.

Cite as: Tennessee — Construction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations (Construction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations), referencesource.org/construction-retainage-limits-by-state/tennessee/, checked 2026-08-16.

What the source says

(a) All construction contracts on any project in this state, both public and private, may provide for the withholding of retainage; provided, however, that the retainage amount may not exceed five percent (5%) of the amount of the contract.

— law.justia.com, retrieved 2026-08-16

Where each value comes from

This source states these in separate places, so each value is shown with the passage that states it.

Release deadline

The owner, whether public or private, shall release and pay all retainages for work completed pursuant to the terms of any contract to the prime contractor within ninety (90) days after completion of the work or within ninety (90) days after substantial completion of the project for work completed, whichever occurs first.

Statutory citation

66-34-103 - Withholding of retainage - Violations - Penalties

— all from law.justia.com, retrieved 2026-08-16