Washington

For Washington, public project retainage cap (%) is 5%; private project retainage cap (%) is 5% of the contract price of the work completed, on private construction projects other than single-family residential construction of less than 12 units (RCW 60.30.010); release deadline is 60 days after completion of all contract work (public improvement contracts, RCW 60.28.011); escrow required is optional; milestone reduction is contractor may request retainage be reduced to 100% of the value of work remaining, recorded from its source on 2026-09-03.

State
Washington our reading
Public project retainage cap (%)
5%
Private project retainage cap (%)
5% of the contract price of the work completed, on private construction projects other than single-family residential construction of less than 12 units (RCW 60.30.010)
Release deadline
60 days after completion of all contract work (public improvement contracts, RCW 60.28.011)
Escrow required
optional
Milestone reduction
contractor may request retainage be reduced to 100% of the value of work remaining
Statutory citation
RCW 60.28.011 (public improvement contracts); RCW 60.30.010 (private construction projects) our reading
Sourceapp.leg.wa.gov
Verified
Review by
DatasetConstruction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations

Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.

Cite as: Washington — Construction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations (Construction retainage limits by US state — maximum withholding percentages, release deadlines, escrow requirements, and public vs private distinctions with statutory citations), referencesource.org/construction-retainage-limits-by-state/washington/, checked 2026-09-03.

What the source says

public improvement contracts must provide, and public bodies must reserve, a contract retainage not to exceed five percent of the moneys earned by the contractor as a trust fund for the protection and payment of: (i) The claims of any person arising under the contract

— app.leg.wa.gov, retrieved 2026-09-03

Where each value comes from

These values are stated in different places, and not all on the same page, so each is shown with the passage that states it and the source that passage came from.

Private project retainage cap (%)

(1) An owner, contractor, subcontractor, or supplier may withhold as retainage an amount equal to not more than five percent of the contract price of the work completed for private construction projects.

— from app.leg.wa.gov, retrieved 2026-09-03

Release deadline

(b) Sixty days after completion of all contract work the public body must release and pay in full the amounts retained during the performance of the contract subject to the provisions of chapter 39.12 RCW and this chapter.

— from app.leg.wa.gov, retrieved 2026-09-03

Escrow required

(4) The moneys reserved by a public body under the provisions of a public improvement contract, at the option of the contractor, must be: (a) Retained in a fund by the public body; (b) Deposited by the public body in an interest bearing account in a bank, mutual savings bank, or savings and loan association. Interest on moneys reserved by a public body under the provision of a public improvement contract must be paid to the contractor; (c) Placed in escrow with a bank or trust company by the public body.

— from app.leg.wa.gov, retrieved 2026-09-03

Milestone reduction

(3) The contractor at any time may request the contract retainage be reduced to one hundred percent of the value of the work remaining on the project.

— from app.leg.wa.gov, retrieved 2026-09-03

Statutory citation

RCW 60.28.011 Retained percentage

— from app.leg.wa.gov, retrieved 2026-09-03