Reference Source

State public works payment and performance bond thresholds (Little Miller Acts)

Do I need a surety bond on this public works project in my state, and how much? Every US state has a 'Little Miller Act' requiring performance and/or payment bonds on public construction contracts, but the dollar thresholds, bond percentages, notice requirements, and claim deadlines differ in every state. California requires bonds on all public works contracts (no minimum) with payment bonds over $25,000. Texas requires bonds over $100,000 for state entities, $25,000 for payment bonds. Washington allows retainage in lieu of bond under $150,000. One record per state, sourced from the state's own statute. Answers 'Little Miller Act thresholds by state', 'do I need a bond on a $75,000 public project in Virginia', 'state payment bond requirements for construction'. Adjacent to mechanics-lien-deadlines, construction-retainage-limits, and construction-prompt-payment-deadlines.

Records53
Sources2
Verified
Review by
Licenceunknown

The data

StatePayment bond thresholdBond amountClaim deadlinePreliminary notice requiredStatutory citationPerformance bond threshold
AlabamaLess than $50,000Not less than 50 percent of the contract pricenot later than one year from the date of final settlement of the contractWritten notice to the surety of the amount claimed to be due and the nature of the claim shall be sent by registered or certified mail 45 days prior to filing suitCode of Alabama, Title 39, Chapter 1, Division 8, §§39-1-1
AlaskaUnder $100,000one-half of the contract price where the total amount payable by the terms of the contract is not more than $1,000,000; 40 percent of the contract price whenever the total amount payable by the terms of the contract is more than $1,000,000 but not more than $5,000,000; whenever the total amount payable by the terms of the contract is more than $5,000,000 the payment bond is in the sum of $2,500,000such action must be commenced within one year after the date of final settlement of the contractAny person having a direct contractual relationship with a subcontractor but no contractual relationship, express or implied, with the principal contractor must give written notice to the contractor within 90 days from the date on which such person performed the last of the labor or furnished or supplied the last of the material for which the claim is madeAlaska Statutes, Title 36, Chapter 36.25, §§36.25.010 to 36.25.020
ArizonaOne hundred percent of the contract pricesuit must be actually filed within one year of the date on which the last of the claimant’s labor was performed or the claimant’s materials were furnishedmust actually serve the prime contractor with written notice of a bond claim, with confirmed receipt, not later than ninety (90) days following the last date that labor was performed or materials were suppliedArizona Revised Statutes, Title 34, Chapter 2, Article 2, §§ 34-222-223Both a performance bond and a payment bond must equal the full contract amount
Arkansasall public works exceeding $20,000A sum equal to the amount of the contractNo action shall be brought on the bond after six months from the final payment on the jobNo special statutory provisionArkansas Code Annotated, Title 18, Subtitle 4, Chapter 44, Subchapter 5, §§18-44-501 to 18-44-508; Title 22, Chapter 9, Subchapter 4, §§22-9-401 to 22-9-405
CaliforniaContracts less than $25,000 are excluded from bond requirementsA sum equal to the amount of the contract on all public worksmust be commenced before the expiration of six months after the period in which stop payment notices may be filedA claimant must give the preliminary notice as required for stop payment notices for public worksCalifornia Civil Code, Division 4, Part 6, Title 2, Chapter 6, §§8600 to 8614; Title 3, Chapter 3, §§9300 to 9306; Chapter 5, §§9550 to 9566
ColoradoAny contract for more than $50,000 with any county, municipality, or school district for the construction of any public building or the prosecution or completion of any public works or for repairs upon any public building or public works. Any contract for more than $100,000 for the construction of any public work for the State of Colorado.not less than one-half of the total amount payable under the terms of the contractWithin six months after the completion of the public workmay file, with the official awarding the contract, a verified statement of the amount due and unpaid§§38-26-102, 38-26-105, 38-26-106, C.R.S.
ConnecticutUnder $100,000A bond in the amount of the contract is requiredNo suit may be commenced after the expiration of one year after the day on which the last of the labor was performed or material was supplied by the claimantmay enforce the right to payment under the bond by serving a written notice of claim within 180 daysConnecticut General Statutes, Title 49, Chapter 847, §§49-41 to 49-42
DelawareA special state body, the Contracting and Purchasing Advisory Council, sets the threshold amount for “large public works” where bonds are required100 percent of the contract priceno suit on the bond shall be commenced after the expiration of one year following the date which the successful bidder ceased work on the contractNo special statutory provision, review bond for timeframesDelaware Code Annotated, Title 29, Chapter 69, §6962
District of ColumbiaProcurement regulations may waive bonds for contracts of $100,000 or less100% of the prime contract amount if over $100,000within one year from the date final labor was performed or the material was suppliedmust give written notice to the prime contractor within 90 days from the date on which the claimant performed the last of the labor or furnished the last of the material for which the claim is madeDistrict of Columbia Code, Division I, Title 2, Chapter 3A, Subchapter VII, §§2-357.01 to 2-357.06
Federal (Miller Act)for construction contracts greater than $35,000, but not greater than $150,000, the contracting officer shall select two or more of the following payment protections100 percent of the original contract price40 U.S.C. chapter 31requires performance and payment bonds for any construction contract exceeding $150,000
FloridaThe threshold for exemption from the bond requirement is $100,000 on public worksIn an amount equal to the original contract priceafter one year from the performance of the labor or completion of delivery of the materials or suppliesshall, within 45 days after beginning to furnish labor, material or supplies for the prosecution of such work, furnish the contractor with a notice that he intends to look to the bond for protectionFlorida Statutes, Title XVIII, Chapter 255, §255.05
GeorgiaLess than $100,000Not less than the contract priceAll suits must be brought within one year after the completion of the project and acceptance by the public authorityThose not under direct contract with the general contractor must give written notice of claim within 90 days after the date on which the last of the labor was performed or the last of the materials furnishedOfficial Code of Georgia, Title 13, Chapter 10, §§13-10-60 to 13-10-65
HawaiiAll public construction projects which exceed $25,000a bond equal to 100 percent of the contract price of constructionshall be brought within one year after the last labor was performed or material supplied for the work provided in the contractWritten notice shall be served by registered or certified mail to contractor and surety within 90 days from the date on which the person did or performed the last labor or furnished or supplied the last of the material for which claim is madeHawaii Revised Statutes, Division 1, Title 9, Chapter 103D, §324
Idahoany contract equal to or greater than fifty thousand dollarsIn an amount to be fixed by the contracting body, but in no event less than eighty-five percent of the contract amountNo such suit shall be commenced after the expiration of one year from the date on which the claimant performed the last of the labor or furnished or supplied the last of the material or equipment for which such suit is broughtmust give written notice to the contractor within 90 days from the date on which such claimant performed the last of the labor or furnished or supplied the last of the material or equipment for which such claim is madeIdaho Statutes, Title 54, §§ 54-5203, 54-5217, 54-1902, 54-1925 to 1929
Illinoisin an amount sufficient to complete the contract including the payment for all labor and materialNo action shall be brought on the bond later than one year after the date of the furnishing of the last item of work or materials by the claimantshall have filed verified notice of claim with the officer, board, bureau or department awarding the contract within 180 days after the date of the last item of work or the furnishing of the last item of materialsIllinois Compiled Statutes, 30 ILCS 550/0.01 to 550/3
IndianaTitle 4, Title 5, Title 8 and Title 36 require bonds for state and local projects in excess of $200,000a bond for the total price of the general contractall suits must be brought against the surety on the payment bond within one year after final settlement with the contractora written Verified Claim stating the amount due and owing to the claimant must be filed with the Public Works Division of the Indiana Department of Administration within 60 days after the last labor performed, last materials furnished or last services renderedIndiana Code, Title 4, Article 13.6, Chapter 7, §§4-13.6-7-5 to 4-13.6-7-11; Title 5, Article 16, Chapter 5, §§5-16-5-1 to 5-16-5-2; Title 8, Article 23, Chapter 9, §§8-23-9-8 to 8-23-9-33; Title 36, Article 1, Chapter 12, §§36-1-12-12 to 36-1-12-13.1
IowaPublic improvement contracts under $25,000Not less than 75 percent of the contract priceAny time after the expiration of 30 days, and not later than 60 days, following the completion and final acceptance of the public improvementSuch notice must be received by the principal contractor within thirty days of first performing or furnishingIowa Code, Title XIV, Subtitle 3, Chapter 573
KansasRequired if the contract exceeds $100,000must be for at least the amount of the contract priceno action shall be brought on the bond after six months from the completion of the public improvementNo special statutory provision, so review bond to determine deadlinesKansas Statutes, Chapter 60, Article 11, §§60-1110 to 60-1111
KentuckyUnder $25,000A payment bond in the amount of 100 percent of the contract pricecivil actions on bonds in the class of procedures which must be initiated within 15 years after cause of action has accruedWithin 60 days of the last day of the month in which materials were provided, the claimant must file a statement in writing verified by affidavitKentucky Revised Statutes, Title XXXI, Chapter 376.100
Louisianaa contract in excess of $25,000 for the construction, alteration or repair of any public worka bond furnished in an amount not less than 50 percent of the contract priceOn public works, one year following the date upon which the notice of termination was filedLouisiana Revised Statutes, Title 9, §§9:4802C, 9:4811 to 9:4812, 9:4823A(2); Title 38, §§38:2212, 38:2241, 38:2246A, 38:2247
Maineany contract exceeding $125,000Both payment and performance bonds in an amount equal to the full contract amountno action may be commenced after the expiration of one year from the date on which the last of the labor was performed or material was suppliedshall have given written notice to the contractor within 90 days from the date on which such claimant performed the last of the labor or furnished or supplied the last of the material for which such claim is madeMaine Revised Statutes, Title 14, Chapter 205, Subchapter 3, §871any contract exceeding $125,000
Marylanda construction contract exceeding $100,00050 percent of the total amount payable under the prime contractno more than one year after the public body finally accepts the work performed under the contractmust give written notice to the prime contractor within 90 days from the date on which the claimant performed the last of the labor or furnished the last of the material for which such claim is madeMaryland Code Annotated, Finance and Procurement, Title 17, §§17-101 to 17-111a construction contract exceeding $100,000
Massachusettsmore than $5,000 in the case of the Commonwealth and more than $2,000 in the case of a contract with a county, city, town, district or other political subdivisionnot less than one-half of the total contact priceWithin one year after the day such claimant last performed the labor or furnished the labor, materials, equipment, appliances or transportation included in his claimmust give notice of a claim in writing to the general contractor within 65 days after the day on which the claimant last performed labor or furnished labor, materials, equipment, appliances or transportationMassachusetts General Laws, Part I, Title XXI, Chapter 149, §§26, 27D, 28, 29, 44A
MichiganAny contract exceeding $50,000 for the construction, alteration, or repair of any public building or public work or improvementEach payment and performance bond shall be in an amount fixed by the government unit to be not less than 25 percent of the contract priceclaimant has within 30 days after furnishing the first of such material or performing the first of such labor served on the principal contractor a written noticeMichigan Compiled Laws, Chapter 129, §129.201Any contract exceeding $50,000 for the construction, alteration, or repair of any public building or public work or improvement
MinnesotaProjects under $100,000Performance and payment bonds each to be not less than the contract pricebegun within one year after the date of the last work by the claimant on the public project as stated in its notice of claimwithin 120 days after completion, delivery or provision by the person of its last item of work, the person serves a written notice of claim personally or by certified mail upon the surety that issued the bond and the contractorMinnesota Statutes, Chapter 574, §§ 574.26 to 574.32
Mississippiin an amount not less than the amount of the contractit shall be commenced within one year after the day on which the last of the labor was performed or material was supplied by the person bringing the actionmust give written notice to the contractor by hand delivery or certified mail within a 90-day period after the date on which the last of the labor was performed by him or the last of the materials was furnished by himMississippi Code Annotated, Title 31, Chapter 5, §§31-5-51 to 31-5-57Whenever a contract is less than $25,000, the owners may elect to make a lump sum payment at the end of the job. In such cases, a performance bond is not required.
Missourirequired to be posted for jobs where the general contract is in excess of $50,000.00A Notice must be served within 90 days of the last furnishing or labor or material to the jobsiteMissouri Revised Statutes, Title 2, Chapter 8, §8.250; Title 4, Chapter 34, §§34.057, 34.058.1
MontanaA school district may waive their requirements of these bonds for contracts under $7,500. Other state or governmental authorities may waive their requirements for under $50,000.Full contract price for state contractswithin 90 days from and after the completion of the contract and the acceptance of the work by the public officialsNot later than 30 days after the date of the first delivery of the provender, material, supplies or provisions to any subcontractorMontana Code, Title 18, Chapter 1, §18-1-402; Chapter 2, §§18-2-201 to 18-2-208, 18-2-316, 18-2-401, 18-2-403, 18-2-409
Nebraskaany project bid or proposed by the State of Nebraska or any department or agency thereof which has a total cost of $15,000 or less, or (b) any project bid or proposed by any county board, contracting board of any city, village, or school district, public board, or officer which has a total cost of $10,000 or lessnot less than the contract priceNo suit shall be commenced after the expiration of one year after the date of final settlement of the principal contractupon giving written notice to the contractor within four months from the date on which such person did or performed the last of the labor or furnished or supplied the last of the materialNebraska Revised Statutes, Chapter 52, §§52-118 to 52-118.02
NevadaContracts less than $100,000 are excluded from bond requirementsThe payment bond shall be not less than 50 percent of the contract priceno such action may be commenced after the expiration of one year from the date on which the claimant performed the last of the labor or furnished the last of the materialif he has, within 30 days after furnishing the first of such materials or performing the first of such labor, served on the contractor a written noticeNevada Revised Statutes, Title 28, Chapter 339, §§ 339.015 to 339.065
New Hampshirean expenditure of $75,000 in behalf of the state or $125,000 in behalf of a political subdivisiona bond in an amount equal to at least 100 percent of the contract priceshall within 90 days after the completion and acceptance of the project by the contracting party file a statement of claimshall within 90 days after the completion and acceptance of the project by the contracting party file a statement of claimNew Hampshire Revised Statutes, Title XLI, Chapter 447, §§447:15 to 447:18
New JerseyThe state may waive the bond requirements on contracts for its public works not in excess of $200,000At least 100 percent of the contract pricewithin one year of the date of last furnishing of materials and laborshall provide the contractor with written notice via certified mail, prior to furnishing work, that such person is a beneficiary under the bondNew Jersey Statutes Annotated, Title 2A, §§2A:44-143 to 44-147
New MexicoFor contracts greater than $25,000not less than one hundred percent (100%) of the contract priceNo suit on the construction payment bond may be commenced after the expiration of one year from the date of final “settlement” of the contract as defined by statutemust serve written notice to the principal contractor within ninety (90) days from the date on which such person performed the last of the labor or furnished or supplied the last of the materialNew Mexico Statutes Annotated, Chapter 13, Section 4, §§ 13-4-1 to 13-4-24; Chapter 48, Section 2A, §§ 48-2A-1 to 48-2A-12
New YorkPayment bond may be waived for public works contracts for less than $50,000No special statutory provisionNo action on a payment bond shall be commenced after the expiration of one year from the date that the public entity accepted the completion of the projectmust give written notice to the contractor within 120 days from the date on which the last of the labor was performed or the last of the material was furnishedNew York Finance Law, Article 9, §137
North CarolinaUnder $300,000 ($500,000 for state contracts)100 percent of the contract priceone year from the day on which the last of the labor was performed or material was furnished by the claimantmust give written notice to the contractor within 120 days from the date on which the claimant performed the last of the labor or furnished the last of the materials for which he claims paymentNorth Carolina General Statutes, Chapter 44A, Article 2, Part 1, §§44A-25 to 44A-35
North Dakotaat least equal to the price stated in the contractupon which a suit is not commenced within one year after completion and acceptance of the project, is barredhas given written notice to the contractor, within 90 days from the date on which the person completed the contributionNorth Dakota Century Code, Title 48, Chapter 48-01.2, §§48-01.2-01 to 48-01.2-25
OhioNo specific statutory provisionsuit must be commenced not later than one year from date of acceptance of the public improvement by the Public Authorityis required to serve a Notice of Furnishing on the principal contractor to preserve bond rights within 21 days of first performing labor or furnishing materialsOhio Statutes, Title 1, Chapter 153, §§153.56, 153.57, 153.571
OklahomaUnder $50,000100 percent of the contract amountNo action shall be brought on said payment bond after one year from the date on which the last of the labor was performed or materials or parts furnishedmust give written notice to the contractor and surety on said payment bond within 90 days from the date on which said person did or performed the last of the labor or furnished or supplied the last of the material or partsOklahoma Statutes, Title 61, §61.2
OregonContracts less than $100,000 are excluded from payment bond requirements; or in the case of contracts for highways, bridges and other transportation projects, less than $50,000a payment bond in an amount equal to the full contract priceA claimant may institute an action on the contractor’s bond not later than two years after the person last provided labor or materialsmust be sent by registered or certified mail or hand delivered no later than 180 days after the day the person last provided labor or furnished materialsOregon Revised Statutes, Volume 7, Title 26, Chapter 279C, §§279C.380, 279C.390, 279C.600 to 279C.625
PennsylvaniaUnder $5,000100 percent of the contract priceAn action upon any payment or performance bond must be commenced after the expiration of 90 days, but within one year, after performancemay bring an action on the payment bond only if he has given written notice to such contractor within 90 days from the date on which the claimant performed the last of the labor or furnished the last of the materialsPennsylvania Consolidated Statutes, Title 8, §§191-202
Puerto RicoNo special statutory provisiona payment bond for not less than one-half the contract amount plus any additions, enlargement or increase theretoSuit must instituted by all claimants within six months after final acceptance of the work by the Commonwealth of Puerto Ricoshall have the right to file suit on the bond without necessity for previous noticePuerto Rico Laws Annotated, Title 22, Chapter 3
Rhode IslandAny public road or portion thereof or any bridge in which the contract price shall be in excess of $50,000 shall be required to furnish a bond; no exclusion provided for other projectsNot less than 50 percent and not more than 100 percent of the contract priceAny time after the expiration of 90 days after the day which the last of the labor was furnished or performed or material or equipment was furnished or supplied by any person claiming, but within two yearsupon giving written notice to the contractor within 90 days of the date on which the person furnished or performed the last labor, materials or suppliesRhode Island General Laws, Chapter 37-12, §§37-12-1 to 37-12-11
South CarolinaUnder $10,000 (highway work)For other public improvement contracts, a performance and payment bond, both equal to 100 percent of the contract pricesuit must be brought within one year after plaintiff last supplied materials or labormust give written notice to contractor within 90 days from the date on which claimant did or performed the last of the labor or furnished or supplied the last of the materialSouth Carolina Code of Laws, Title 29, Chapter 5, §29-5-440For public highway construction contracts, a performance bond for 100 percent of the contract and in no case less than $10,000
South DakotaThe state may waive the bond requirement on contracts of less than $50,000 for any public improvementmay be issued for the total cost of the improvementsA party may not sue for payment until six months after complete performance of the obligations of the contract for improvementNotice of a suit must be given to all known creditors informing each of their right to interveneSouth Dakota Codified Laws, Title 5, Chapter 18A, §5-18A-14. Title 5, Chapter 21, §§5-21-1 to 5-21-8. Title 9, Chapter 44, §9-44-3
Tennesseeall public contracts (except highways) in excess of $100,000Bond shall be 25 percent of the contract price on all public contracts (except highways) in excess of $100,000an action shall be brought or claims so filed within six months following the completion of such public workshall, after such labor or material is furnished and within 90 days after the completion of such public work, give written notice to either the contractor who executed the bond or the public officialTennessee Code, Title 12, Chapter 4, Part 2, §§12-4-201 to 12-4-206; Title 54, Chapter 5, Part 1, 54-5-119 to 54-5-127
TexasWhen the governmental entity is not a municipality or a joint board created under Subchapter D, Chapter 22 of the Transportation Code, contracts excluded are those less than $25,000. When the governmental entity is a municipality or a joint board created under Subchapter D, Chapter 22 of the Transportation Code, contracts excluded are those less than $50,000.The amount of the contractNo suit may be brought on the payment bond after the expiration of one year after the date the notice of claim is mailedmust mail to the prime contractor and the surety written notice of the claim on or before the 15th day of the third month after each month in which any of the claimed labor was performedTexas Government Code, Title 10, Subtitle F, Chapters 2253, 2267
UtahThere are no contracts excludedA payment bond must be in an amount equal to 100 percent of the price specified in the contractto one year after the date of last supplied, labor, service, equipment and/or material for which the claim is madea preliminary notice must be filed with the State Construction Registry before making a payment bond claimUtah Code, Title 14, Chapter 1, §§14-1-18 to 14-1-20; Title 38, Chapter 1b, §§38-1b-101 to 38-1b-203; Title 63G, Chapter 6, §§63G-6-505, 63G-6-506
VermontThe Agency of Transportation has the power to require any contractor employed in a state project to file a surety bondWithin one year after filing the claim, the claimant must file suit in Superior CourtClaimants must file a sworn statement of claim under the bond with the secretary within 90 days after final acceptance of the project by the stateVermont Statutes, Title 19, Chapter 1, §10
Virginiaall public construction contracts exceeding $500,000 and all state transportation related projects exceeding $350,000Payment bonds in the sum of the prime contract amountwithin one year after the day on which the claimant last performed labor or last furnished materialsmust give written notice of the bond claim to the prime contractor within 90 days from the date on which the claimant performed the last labor or furnished the last materialCode of Virginia, Title 2.2, Chapter 43, §§2.2-4337 to 2.2-4341
WashingtonAny contract for a public improvement by Washington State, or any county, municipality or other public body within Washington, requires a surety bond100 percent of the contract amountNo special statutory provision for suit against payment bond is in the statute but it is subject to the general six-year statute of limitations for contract actionsshall, not later than 10 days after the date of the first delivery of such materials or supplies, deliver or mail a notice to the contractorRCW 39.08.010, RCW 39.08.030(1)(a)when the contract is for $150,000 or less, then at the option of the contractor or the general contractor/construction manager as defined in RCW 39.10.210, the public body may retain 10 percent of the contract price
West Virginiacounty boards of education shall require all persons contracting for the building or repairing of school property, where the contract exceeds $10,000, to execute a bondpenal sum equal at least to the reasonable cost of the materials, machinery, equipment and labor required for the completion of said contractWest Virginia Code, Chapter 5, §§5-6-7, 5-22-1; Chapter 17, §17-4-20; Chapter 18, §18-5-12; Chapter 38, §§38-2-21, 38-2-34, 38-2-39
Wisconsinthe state may not require a bond on contracts not exceeding $148,000. On contracts with local governments, the local government may not require a bond on contracts not exceeding $74,000At least equal to contract priceNo later than one year after the completion of the work under the contractwithin 60 days after the first provision of labor or materials, notified the prime contractor in writingWisconsin Statutes, Chapter 779, §779.15, cited as Wis. Stat. §779.15
Wyoming$7,500 or underNot less than one-half of the contract price, except where such price exceeds $150,000, in which case the bond shall be in such amount as the appropriate officer, agency or governing body deemed sufficientSuit must be brought within one year after the date of the first publication of notice of final payment of the contractSubcontractors or materialmen on projects of $50,000 or more must give written notice to the general contractor of his rights under the bond within 60 days of first providing labor or materialsWyoming Statutes, Title 16, Chapter 6, Article 1, §§16-6-101 to 16-6-121

Where this came from

Every record above links the page it was taken from and quotes the sentence that states it. These are the 2 sources this dataset was assembled from.

Machine-readable

53 records. last verified against source . due for re-check by .

Licence. unknown