Maine
What is the performance bond threshold for Maine?
For Maine, performance bond threshold is any contract exceeding $125,000; payment bond required above is any contract exceeding $125,000; bond amount is Both payment and performance bonds in an amount equal to the full contract amount; claim deadline is no action may be commenced after the expiration of one year from the date on which the last of the labor was performed or material was supplied; preliminary notice required is shall have given written notice to the contractor within 90 days from the date on which such claimant performed the last of the labor or furnished or supplied the last of the material for which such claim is made, verified against its source on 2026-11-19.
MAINE Bonds Required: Bonds are required in Maine regarding any contract exceeding $125,000 for the construction, alteration or repair of any public building or other public improvement or public work.
— fullertonlaw.com, retrieved 2026-08-17
- State
- Maine our reading
- Performance bond threshold
- any contract exceeding $125,000 verified
- Payment bond required above
- any contract exceeding $125,000 verified
- Bond amount
- Both payment and performance bonds in an amount equal to the full contract amount verified
- Claim deadline
- no action may be commenced after the expiration of one year from the date on which the last of the labor was performed or material was supplied verified
- Preliminary notice required
- shall have given written notice to the contractor within 90 days from the date on which such claimant performed the last of the labor or furnished or supplied the last of the material for which such claim is made verified
- Statutory citation
- Maine Revised Statutes, Title 14, Chapter 205, Subchapter 3, §871 verified
Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.
Cite as: Maine — State public works payment bond requirements (Little Miller Acts) (State public works payment bond requirements (Little Miller Acts)), referencesource.org/state-public-works-bond-thresholds/maine/, checked 2026-11-19.
Where each value comes from
This source states these in separate places, so each value is shown with the passage that states it.
Bond amount
Both payment and performance bonds in an amount equal to the full contract amount.
Claim deadline
Time for Suit: No suit shall be commenced prior to 90 days from the date on which claimant furnished the last of the labor or material for which such claim is made and no action may be commenced after the expiration of one year from the date on which the last of the labor was performed or material was supplied for the payment of which such action is brought.
Preliminary notice required
A claimant having a direct contractual relationship with a subcontractor of the contractor (but no contractual relationship, express or implied, with such contractor) shall not have the right of action upon such payment bond unless he shall have given written notice to the contractor within 90 days from the date on which such claimant performed the last of the labor or furnished or supplied the last of the material for which such claim is made, stating with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or supplied or for whom the labor was done or performed.
Statutory citation
Statutory Citation: Maine Revised Statutes, Title 14, Chapter 205, Subchapter 3, §871.
— all from fullertonlaw.com, retrieved 2026-08-17