What is the performance bond threshold for Maryland?

For Maryland, performance bond threshold is a construction contract exceeding $100,000; payment bond required above is a construction contract exceeding $100,000; bond amount is 50 percent of the total amount payable under the prime contract; claim deadline is no more than one year after the public body finally accepts the work performed under the contract; preliminary notice required is must give written notice to the prime contractor within 90 days from the date on which the claimant performed the last of the labor or furnished the last of the material for which such claim is made, verified against its source on 2026-11-19.

MARYLAND Amount of Bond: 50 percent of the total amount payable under the prime contract.

— fullertonlaw.com, retrieved 2026-08-17

State
Maryland our reading
Performance bond threshold
a construction contract exceeding $100,000 verified
Payment bond required above
a construction contract exceeding $100,000 verified
Bond amount
50 percent of the total amount payable under the prime contract verified
Claim deadline
no more than one year after the public body finally accepts the work performed under the contract verified
Preliminary notice required
must give written notice to the prime contractor within 90 days from the date on which the claimant performed the last of the labor or furnished the last of the material for which such claim is made verified
Statutory citation
Maryland Code Annotated, Finance and Procurement, Title 17, §§17-101 to 17-111 verified
Sourcefullertonlaw.com
Verified
Review by
DatasetState public works payment bond requirements (Little Miller Acts)

Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.

Cite as: Maryland — State public works payment bond requirements (Little Miller Acts) (State public works payment bond requirements (Little Miller Acts)), referencesource.org/state-public-works-bond-thresholds/maryland/, checked 2026-11-19.

Where each value comes from

This source states these in separate places, so each value is shown with the passage that states it.

Performance bond threshold and Payment bond required above

Before a public body awards a construction contract exceeding $100,000, the contractor must provide payment security and performance security that meet the requirements of § 17-104 of this subtitle, in an amount that the public body considers adequate for its protection; and for payment security, at least 50 percent of the total amount payable under the contract.

Claim deadline

Time for Suit: Suit must be instituted more than 90 days after the day on which the claimant last supplied labor or materials for which the claim is made, but no more than one year after the public body finally accepts the work performed under the contract.

Preliminary notice required

Any claimant having a contract with a subcontractor, or with any sub-subcontractor must give written notice to the prime contractor within 90 days from the date on which the claimant performed the last of the labor or furnished the last of the material for which such claim is made, stating with substantial accuracy the amount claimed and the name of the party to whom the material was furnished, or for whom the labor was performed.

Statutory citation

Statutory Citation: Maryland Code Annotated, Finance and Procurement, Title 17, §§17-101 to 17-111.

— all from fullertonlaw.com, retrieved 2026-08-17

Source

Last verified against source: . Due for re-check by . This page as Markdown · OKF bundle · full dataset as JSON.

Want this list kept current for you?The whole dataset as CSV and JSON, every value with its source and the quote it came from, re-checked and re-sent — $9 a month. What you get, and how to ask for it.