North Dakota
What is the bond amount for North Dakota?
For North Dakota, bond amount is at least equal to the price stated in the contract; claim deadline is upon which a suit is not commenced within one year after completion and acceptance of the project, is barred; preliminary notice required is has given written notice to the contractor, within 90 days from the date on which the person completed the contribution; statutory citation is North Dakota Century Code, Title 48, Chapter 48-01.2, §§48-01.2-01 to 48-01.2-25, verified against its source on 2026-11-19.
NORTH DAKOTA Amount of Bond: The amount of a bond obtained from a contractor on a public project shall be at least equal to the price stated in the contract.
— fullertonlaw.com, retrieved 2026-08-17
- State
- North Dakota our reading
- Bond amount
- at least equal to the price stated in the contract verified
- Claim deadline
- upon which a suit is not commenced within one year after completion and acceptance of the project, is barred verified
- Preliminary notice required
- has given written notice to the contractor, within 90 days from the date on which the person completed the contribution verified
- Statutory citation
- North Dakota Century Code, Title 48, Chapter 48-01.2, §§48-01.2-01 to 48-01.2-25 verified
Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.
Cite as: North Dakota — State public works payment bond requirements (Little Miller Acts) (State public works payment bond requirements (Little Miller Acts)), referencesource.org/state-public-works-bond-thresholds/north-dakota/, checked 2026-11-19.
Where each value comes from
This source states these in separate places, so each value is shown with the passage that states it.
Claim deadline
Time for Suit: Any claim for any labor, material, or supply furnished for an improvement, upon which a suit is not commenced within one year after completion and acceptance of the project, is barred as a lien or claim against the contractor and the contractor’s surety and any right of setoff or counterclaim may be enforced in any court in this state against the governing body, the contractor, or the contractor’s surety.
Preliminary notice required
However, a person having a direct contractual relationship with a subcontractor, but no contractual relationship with the contractor furnishing the bond, does not have a claim for relief upon the bond unless that person has given written notice to the contractor, within 90 days from the date on which the person completed the contribution, stating with substantial accuracy the amount claimed and the name of the person for which the contribution was performed.
Statutory citation
Statutory Citation: North Dakota Century Code, Title 48, Chapter 48-01.2, §§48-01.2-01 to 48-01.2-25.
— all from fullertonlaw.com, retrieved 2026-08-17
Source
- fullertonlaw.comhttps://fullertonlaw.com/50-state-summary-payment-bond-law