Ohio
What is the contracts excluded for Ohio?
For Ohio, contracts excluded is No specific statutory provision; claim deadline is suit must be commenced not later than one year from date of acceptance of the public improvement by the Public Authority; preliminary notice required is is required to serve a Notice of Furnishing on the principal contractor to preserve bond rights within 21 days of first performing labor or furnishing materials; statutory citation is Ohio Statutes, Title 1, Chapter 153, §§153.56, 153.57, 153.571, verified against its source on 2026-11-19.
OHIO Types of Projects: The bond for Public Projects is a combination bid bond, performance bond and payment bond.
— fullertonlaw.com, retrieved 2026-08-17
- State
- Ohio our reading
- Contracts excluded
- No specific statutory provision verified
- Claim deadline
- suit must be commenced not later than one year from date of acceptance of the public improvement by the Public Authority verified
- Preliminary notice required
- is required to serve a Notice of Furnishing on the principal contractor to preserve bond rights within 21 days of first performing labor or furnishing materials verified
- Statutory citation
- Ohio Statutes, Title 1, Chapter 153, §§153.56, 153.57, 153.571 verified
Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.
Cite as: Ohio — State public works payment bond requirements (Little Miller Acts) (State public works payment bond requirements (Little Miller Acts)), referencesource.org/state-public-works-bond-thresholds/ohio/, checked 2026-11-19.
Where each value comes from
This source states these in separate places, so each value is shown with the passage that states it.
Contracts excluded
Contracts Excluded: No specific statutory provision.
Claim deadline
Time for Suit: No suit shall be brought against the surety until after 60 days after the furnishing of the statement, but suit must be commenced not later than one year from date of acceptance of the public improvement by the Public Authority.
Preliminary notice required
Notice Required: In order to preserve a bond claim on a public project in Ohio, any subcontractor, laborer or materialman who is not in direct contract with the principal (original) contractor, and who are supplying labor or materials that cost more than $30,000, is required to serve a Notice of Furnishing on the principal contractor to preserve bond rights within 21 days of first performing labor or furnishing materials.
Statutory citation
Statutory Citation: Ohio Statutes, Title 1, Chapter 153, §§153.56, 153.57, 153.571,
— all from fullertonlaw.com, retrieved 2026-08-17
Source
- fullertonlaw.comhttps://fullertonlaw.com/50-state-summary-payment-bond-law
Open the page on fullertonlaw.com that states this — the page quoted above, at its publisher. Unpaid: we earn nothing from this link and it is not an advertisement.