Reference Source

Virginia

What is the payment bond required above for Virginia?

For Virginia, payment bond required above is all public construction contracts exceeding $500,000 and all state transportation related projects exceeding $350,000; bond amount is Payment bonds in the sum of the prime contract amount; claim deadline is within one year after the day on which the claimant last performed labor or last furnished materials; preliminary notice required is must give written notice of the bond claim to the prime contractor within 90 days from the date on which the claimant performed the last labor or furnished the last material; statutory citation is Code of Virginia, Title 2.2, Chapter 43, §§2.2-4337 to 2.2-4341, verified against its source on 2026-11-19.

VIRGINIA Amount of Bond: Payment bonds in the sum of the prime contract amount required on all public construction contracts exceeding $500,000 and all state transportation related projects exceeding $350,000.

— fullertonlaw.com, retrieved 2026-08-17

State
Virginia our reading
Payment bond required above
all public construction contracts exceeding $500,000 and all state transportation related projects exceeding $350,000 verified
Bond amount
Payment bonds in the sum of the prime contract amount verified
Claim deadline
within one year after the day on which the claimant last performed labor or last furnished materials verified
Preliminary notice required
must give written notice of the bond claim to the prime contractor within 90 days from the date on which the claimant performed the last labor or furnished the last material verified
Statutory citation
Code of Virginia, Title 2.2, Chapter 43, §§2.2-4337 to 2.2-4341 verified
Sourcefullertonlaw.com
Verified
Review by
DatasetState public works payment bond requirements (Little Miller Acts)

Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.

Cite as: Virginia — State public works payment bond requirements (Little Miller Acts) (State public works payment bond requirements (Little Miller Acts)), referencesource.org/state-public-works-bond-thresholds/virginia/, checked 2026-11-19.

Where each value comes from

This source states these in separate places, so each value is shown with the passage that states it.

Claim deadline

Time for Suit: Suit must be instituted more than 90 days after the last day labor or material was supplied for which payment is claimed, but within one year after the day on which the claimant last performed labor or last furnished materials.

Preliminary notice required

Claimant having a contract with a subcontractor must give written notice of the bond claim to the prime contractor within 90 days from the date on which the claimant performed the last labor or furnished the last material for which he claims payment, stating with substantial accuracy the amount claimed and the name of the party to whom the work was performed or to whom the material was furnished.

Statutory citation

Statutory Citation: Code of Virginia, Title 2.2, Chapter 43, §§2.2-4337 to 2.2-4341.

— all from fullertonlaw.com, retrieved 2026-08-17

Source

Last verified against source: . Due for re-check by . This page as Markdown · OKF bundle · full dataset as JSON.

Want this list kept current for you?The whole dataset as CSV and JSON, every value with its source and the quote it came from, re-checked and re-sent — $9 a month. What you get, and how to ask for it.