What is the payment bond required above for Kansas?

For Kansas, payment bond required above is Required if the contract exceeds $100,000; bond amount is must be for at least the amount of the contract price; claim deadline is no action shall be brought on the bond after six months from the completion of the public improvement; preliminary notice required is No special statutory provision, so review bond to determine deadlines; statutory citation is Kansas Statutes, Chapter 60, Article 11, §§60-1110 to 60-1111, verified against its source on 2026-11-19.

KANSAS Types of Projects: Can be on private or public projects.

— fullertonlaw.com, retrieved 2026-08-17

State
Kansas our reading
Payment bond required above
Required if the contract exceeds $100,000 verified
Bond amount
must be for at least the amount of the contract price verified
Claim deadline
no action shall be brought on the bond after six months from the completion of the public improvement verified
Preliminary notice required
No special statutory provision, so review bond to determine deadlines verified
Statutory citation
Kansas Statutes, Chapter 60, Article 11, §§60-1110 to 60-1111 verified
Sourcefullertonlaw.com
Verified
Review by
DatasetState public works payment bond requirements (Little Miller Acts)

Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.

Cite as: Kansas — State public works payment bond requirements (Little Miller Acts) (State public works payment bond requirements (Little Miller Acts)), referencesource.org/state-public-works-bond-thresholds/kansas/, checked 2026-11-19.

Where each value comes from

This source states these in separate places, so each value is shown with the passage that states it.

Payment bond required above

Public. Required if the contract exceeds $100,000, and must be for at least the amount of the contract price.

Bond amount

Types of Projects: Can be on private or public projects. The bond must be filed with the Clerk of the District Court of the county where the improvement is to be made. Private. Optional, but if obtained, must be sufficient to pay all claims which might be a basis for a lien, for at least the amount of the contract price. Public. Required if the contract exceeds $100,000, and must be for at least the amount of the contract price.

Claim deadline

Time for Suit: On bonds other than state highway bonds, no action shall be brought on the bond after six months from the completion of the public improvement. On bonds given in connection with the construction, improvement, reconstruction and maintenance of the state highway system, no action may be brought after one year from the completion of the contract.

Preliminary notice required

Notice Required: No special statutory provision, so review bond to determine deadlines, except in connection with the improvement of highways.

Statutory citation

Statutory Citation: Kansas Statutes, Chapter 60, Article 11, §§60-1110 to 60-1111.

— all from fullertonlaw.com, retrieved 2026-08-17

Source

Open the page on fullertonlaw.com that states this — the page quoted above, at its publisher. Unpaid: we earn nothing from this link and it is not an advertisement.