West Virginia
For West Virginia, payment bond threshold is county boards of education shall require all persons contracting for the building or repairing of school property, where the contract exceeds $10,000, to execute a bond; bond amount is penal sum equal at least to the reasonable cost of the materials, machinery, equipment and labor required for the completion of said contract; statutory citation is West Virginia Code, Chapter 5, §§5-6-7, 5-22-1; Chapter 17, §17-4-20; Chapter 18, §18-5-12; Chapter 38, §§38-2-21, 38-2-34, 38-2-39, verified against its source on 2026-08-17.
- State
- West Virginia our reading
- Payment bond threshold
- county boards of education shall require all persons contracting for the building or repairing of school property, where the contract exceeds $10,000, to execute a bond verified
- Bond amount
- penal sum equal at least to the reasonable cost of the materials, machinery, equipment and labor required for the completion of said contract verified
- Statutory citation
- West Virginia Code, Chapter 5, §§5-6-7, 5-22-1; Chapter 17, §17-4-20; Chapter 18, §18-5-12; Chapter 38, §§38-2-21, 38-2-34, 38-2-39 verified
Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.
What the source says
WEST VIRGINIA Amount of Bond : In contracts for the construction, alteration or repair of public buildings other than school edifices, penal sum equal at least to the reasonable cost of the materials, machinery, equipment and labor required for the completion of said contract. In the case of highway work, in such penal sum as the State Road Commissioner shall require, but not to exceed the contract price. With respect to school construction, county boards of education shall require all persons contracting for the building or repairing of school property, where the contract exceeds $10,000, to execute a bond, with approved security, in the amount of the contract price. Labor and Material Covered: All materials, machinery, equipment and labor delivered to the contractor for use in the erection, construction, improvement, alteration or repair of any public building used or to be used for public purposes. Contracts Excluded: No special statutory provision. However, see Payment is an Affirmative Defense (or Partial Defense) for Certain Owners discussed above. West Virginia Code §§38-2-21, 38-2-34. Penalty for Failure to Take Bond: No special statutory provision. Statutory Citation: West Virginia Code, Chapter 5, §§5-6-7, 5-22-1; Chapter 17, §17-4-20; Chapter 18, §18-5-12; Chapter 38, §§38-2-21, 38-2-34, 38-2-39.
— fullertonlaw.com, retrieved 2026-08-17
Source
- fullertonlaw.comhttps://fullertonlaw.com/50-state-summary-payment-bond-law