What is the payment bond required above for New Hampshire?
For New Hampshire, payment bond required above is an expenditure of $75,000 in behalf of the state or $125,000 in behalf of a political subdivision; bond amount is a bond in an amount equal to at least 100 percent of the contract price; claim deadline is Within one year of the claim filing; preliminary notice required is shall within 90 days after the completion and acceptance of the project by the contracting party file a statement of claim; statutory citation is New Hampshire Revised Statutes, Title XLI, Chapter 447, §§447:15 to 447:18, verified against its source on 2026-11-19.
NEW HAMPSHIRE Amount of Bond: NH public projects, shall if said contract involves an expenditure of $75,000 in behalf of the state or $125,000 in behalf of a political subdivision, and may if it involves an expenditure of less amount, be secured by a bond in an amount equal to at least 100 percent of the contract price, or of the estimated cost of the work if no aggregate price is agreed upon.
— fullertonlaw.com, retrieved 2026-08-17
- State
- New Hampshire our reading
- Payment bond required above
- an expenditure of $75,000 in behalf of the state or $125,000 in behalf of a political subdivision verified
- Bond amount
- a bond in an amount equal to at least 100 percent of the contract price verified
- Claim deadline
- Within one year of the claim filing verified
- Preliminary notice required
- shall within 90 days after the completion and acceptance of the project by the contracting party file a statement of claim verified
- Statutory citation
- New Hampshire Revised Statutes, Title XLI, Chapter 447, §§447:15 to 447:18 verified
Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.
Cite as: New Hampshire — State public works payment bond requirements (Little Miller Acts) (State public works payment bond requirements (Little Miller Acts)), referencesource.org/state-public-works-bond-thresholds/new-hampshire/, checked 2026-11-19.
Where each value comes from
This source states these in separate places, so each value is shown with the passage that states it.
Claim deadline
Time for Suit: Within one year of the claim filing.
Preliminary notice required
Notice Required: In order to obtain the benefit of such bond any person, firm or corporation having any claim for labor performed, materials, machinery, tools or equipment furnished, shall within 90 days after the completion and acceptance of the project by the contracting party file a statement of claim.
Statutory citation
Statutory Citation: New Hampshire Revised Statutes, Title XLI, Chapter 447, §§447:15 to 447:18.