Arizona
What is the bond amount for Arizona?
For Arizona, bond amount is One hundred percent of the contract price; claim deadline is suit must be actually filed within one year of the date on which the last of the claimant’s labor was performed or the claimant’s materials were furnished; preliminary notice required is must actually serve the prime contractor with written notice of a bond claim, with confirmed receipt, not later than ninety (90) days following the last date that labor was performed or materials were supplied; statutory citation is Arizona Revised Statutes, Title 34, Chapter 2, Article 2, §§ 34-222-223, verified against its source on 2026-11-19.
Amount of Bond: One hundred percent of the contract price solely for the protection of claimants supplying labor or material to the contractor or his subcontractors in the prosecution of the work provided for in contracts for the construction, alteration, or repair of the public work.
— fullertonlaw.com, retrieved 2026-08-17
- State
- Arizona our reading
- Bond amount
- One hundred percent of the contract price verified
- Claim deadline
- suit must be actually filed within one year of the date on which the last of the claimant’s labor was performed or the claimant’s materials were furnished verified
- Preliminary notice required
- must actually serve the prime contractor with written notice of a bond claim, with confirmed receipt, not later than ninety (90) days following the last date that labor was performed or materials were supplied verified
- Statutory citation
- Arizona Revised Statutes, Title 34, Chapter 2, Article 2, §§ 34-222-223 verified
Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.
Cite as: Arizona — State public works payment bond requirements (Little Miller Acts) (State public works payment bond requirements (Little Miller Acts)), referencesource.org/state-public-works-bond-thresholds/arizona/, checked 2026-11-19.
Where each value comes from
This source states these in separate places, so each value is shown with the passage that states it.
Claim deadline
A.R.S. § 34-223(A). However, suit must be actually filed within one year of the date on which the last of the claimant’s labor was performed or the claimant’s materials were furnished for which the claim is being made.
Preliminary notice required
Otherwise, in order to make a claim on the payment bond, a subcontractor or materials supplier must have served a written preliminary 20-day notice in compliance with A.R.S. § 33.992.01(C), (E), (F) and (H); see A.R.S. §34-223(A)(1). Further, the subcontractor or materials supplier, in addition to serving a preliminary notice, must actually serve the prime contractor with written notice of a bond claim, with confirmed receipt, not later than ninety (90) days following the last date that labor was performed or materials were supplied.
Statutory citation
Statutory Citation: Arizona Revised Statutes, Title 34, Chapter 2, Article 2, §§ 34-222-223.
— all from fullertonlaw.com, retrieved 2026-08-17
Source
- fullertonlaw.comhttps://fullertonlaw.com/50-state-summary-payment-bond-law
Open the page on fullertonlaw.com that states this — the page quoted above, at its publisher. Unpaid: we earn nothing from this link and it is not an advertisement.