For Missouri, preliminary notice required is conditional — subcontractors and suppliers must serve Ten-Day Notice of Intent to File Mechanic's Lien at least 10 days before recording; GC on owner-occupied residential must deliver Notice of Rights before receiving any payment; notice name is Ten-Day Notice of Intent to File Mechanic's Lien; notice deadline — gc (days) is not required (except owner-occupied residential: before receiving any payment); notice deadline — sub/supplier (days) is at least 10 days before recording Statement of Lien; lien recording deadline — gc (days) is 180, recorded from its source on 2026-08-14.
- State
- Missouri verified
- Preliminary notice required
- conditional — subcontractors and suppliers must serve Ten-Day Notice of Intent to File Mechanic's Lien at least 10 days before recording; GC on owner-occupied residential must deliver Notice of Rights before receiving any payment our reading
- Notice name
- Ten-Day Notice of Intent to File Mechanic's Lien
- Notice deadline — GC (days)
- not required (except owner-occupied residential: before receiving any payment)
- Notice deadline — sub/supplier (days)
- at least 10 days before recording Statement of Lien
- Lien recording deadline — GC (days)
- 180
- Lien recording deadline — sub/supplier (days)
- 180
- Enforcement deadline (days)
- 180
- Late notice consequence
- forfeiture our reading
- Statute
- Missouri Revised Statutes Chapter 429 verified
Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.
What the source says
Missouri MO Construction Law Missouri Mechanic Lien Guide and FAQs Your Complete Guide to Mechanic Lien Rights Under Missouri Revised Statutes Chapter 429 —
— mechanicslien.com, retrieved 2026-08-14
Source
- mechanicslien.comhttps://mechanicslien.com/missouri