Mississippi

For Mississippi, preliminary notice required is conditional — not required for GC or direct subs; remote claimants not in privity with owner must serve Pre-Lien Notice within 30 days of first delivery; notice name is Pre-Lien Notice; notice deadline — gc (days) is not required; notice deadline — sub/supplier (days) is not required; lien recording deadline — gc (days) is 90, recorded from its source on 2026-08-14.

State
Mississippi verified
Preliminary notice required
conditional — not required for GC or direct subs; remote claimants not in privity with owner must serve Pre-Lien Notice within 30 days of first delivery our reading
Notice name
Pre-Lien Notice verified
Notice deadline — GC (days)
not required verified
Notice deadline — sub/supplier (days)
not required verified
Lien recording deadline — GC (days)
90 verified
Lien recording deadline — sub/supplier (days)
90 verified
Enforcement deadline (days)
180 verified
Late notice consequence
none our reading
Statute
Mississippi Code Annotated §85-7-131 et seq.
Sourcemechanicslien.com
Verified
Review by
DatasetMechanics lien filing deadlines, preliminary notice requirements, and enforcement windows by US state and party role

Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.

What the source says

File Mechanic Lien Enforcement 180 days Commence the action to enforce the Claim of Lien within 180 days after recording. File a Lawsuit Mississippi private project deadlines Prime Contractor Preliminary Notice: Not required. A prime contractor in privity with the owner has no Pre-Lien Notice obligation. Mechanic Lien: Record the Claim of Lien with the chancery clerk within 90 days after last furnishing labor or materials.

mechanicslien.com, retrieved 2026-08-14