Montana

For Montana, preliminary notice required is conditional — required for subcontractors on residential projects (1-4 units) and non-commercial improvements; not required for GCs, commercial improvements, buildings for 5+ families, or laborers; notice name is Notice of Right to Claim a Construction Lien; notice deadline — gc (days) is not required; notice deadline — sub/supplier (days) is 20 days after first furnishing (or 45 days if funded by regulated lender and not owner's residence); lien recording deadline — gc (days) is 90, recorded from its source on 2026-08-14.

State
Montana verified
Preliminary notice required
conditional — required for subcontractors on residential projects (1-4 units) and non-commercial improvements; not required for GCs, commercial improvements, buildings for 5+ families, or laborers our reading
Notice name
Notice of Right to Claim a Construction Lien
Notice deadline — GC (days)
not required verified
Notice deadline — sub/supplier (days)
20 days after first furnishing (or 45 days if funded by regulated lender and not owner's residence)
Lien recording deadline — GC (days)
90 verified
Lien recording deadline — sub/supplier (days)
90 verified
Enforcement deadline (days)
730
Late notice consequence
partial — A late notice does not kill the lien, it shrinks it. The lien then reaches only what you furnished in the 20 days before the notice was served, plus everything after our reading
Statute
Montana Rev. Code §71-3-501 et seq. verified
Sourcemechanicslien.com
Verified
Review by
DatasetMechanics lien filing deadlines, preliminary notice requirements, and enforcement windows by US state and party role

Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.

What the source says

Montana Rev. Code §71-3-501 et seq. — Private Works, Payment Bonds & Public Projects <https://app.mechanicslien.com/?mode=sign-up> Create Your Account <https://www.mechanicslien.com/get-help/montana> File a Claim <tel:+18004327799> Call (800) 432-7799 Free MT Deadline Calculator Calculate your Montana deadlines and get a free consultation. Montana mechanic lien deadline table with toggles for project type and claimant type. Montana Preliminary Notice & Mechanic Lien Deadlines Select your project type and role to see the deadlines that apply to you. Project Type Private Projects Public Works Property Classification Select Your Tier Prime Contractor Subcontractors & Suppliers Remote Claimants Laborers & Wage Earners Prime Contractor — In direct contract with the property owner, including an architect, engineer, or surveyor the owner hired directly Preliminary Notice Mechanic Lien Enforcement Not Required 90

mechanicslien.com, retrieved 2026-08-14