Vermont

For Vermont, governing body is Department of Public Safety, Division of Fire Safety; statute citation is Vermont Statutes Annotated, Title 20 VSA, Chapter 173, Subchapter 5, Vermont Fire & Building Safety Code - 2015; power boiler inspection interval is Annual internal and external inspection while not under pressure; External inspection, while in operation and under pressure, approximately six months from the internal inspection; low-pressure boiler inspection interval is 2 year external inspection; 2 year internal inspection, where construction permits; pressure vessel inspection interval is 3 year external inspection; 3 year internal inspection, where construction permits, recorded from its source on 2026-08-05.

State
Vermont
Governing body
Department of Public Safety, Division of Fire Safety
Statute citation
Vermont Statutes Annotated, Title 20 VSA, Chapter 173, Subchapter 5, Vermont Fire & Building Safety Code - 2015.
Power boiler inspection interval
Annual internal and external inspection while not under pressure; External inspection, while in operation and under pressure, approximately six months from the internal inspection verified
Low-pressure boiler inspection interval
2 year external inspection; 2 year internal inspection, where construction permits verified
Pressure vessel inspection interval
3 year external inspection; 3 year internal inspection, where construction permits
Accepted inspector types
Inspections made by inspectors with a National Board commission and commissioned by the department are required.
Exemptions
Boilers or pressure vessels located on common carriers subject to Surface Transportation Board, US Department of Transportation, Federal Railroad Administration, or Nuclear Regulatory Commission; Hot-water heaters and potable water storage tanks with heat input of less than 200,000 BTU per hour, water temperature less than 210°F, water-containing capacity less than 120 gallons
Sourcenationalboard.org
Verified2026-08-05
Review by2027-08-05
DatasetUS boiler and pressure vessel inspection requirements by state

What the source says

High pressure power boilers (more than 15 psi) and high temperature water boilers: Annual internal and external inspection while not under pressure; External inspection, while in operation and under pressure, approximately six months from the internal inspection. Low-pressure hot water heating boilers (not exceeding 160 psi and/or temperatures not exceeding 250 degrees) and low-pressure steam boilers (not exceeding 15 psi): 2 year external inspection; 2 year internal inspection, where construction permits, for steam heating boiler (not exceeding 15 psi).

nationalboard.org, retrieved 2026-08-05

Source

Last verified against source: 2026-08-05. Due for re-check by 2027-08-05. This page as Markdown · OKF bundle · full dataset as JSON.