What is the delegated authority for Georgia?

For Georgia, delegated authority is Georgia Environmental Protection Division, Lead-Based Paint and Asbestos Program; notification trigger threshold is All demolitions regardless of asbestos amount; any project involving ten (10) or more continuous linear feet or ten (10) or more square feet of asbestos-containing material for renovations/abatement; advance notice days is ten (10) working day; notification fee is $0.10 per square foot of friable asbestos-containing materials plus $0.10 linear foot of friable asbestos-containing materials, with a minimum of $25 for any project; but not to exceed $50 for any small project or residential dwelling project nor exceed $1,000 for any other project; residential exemption is Legal owners or residences where four (4) or fewer dwelling units are involved, unless part of a larger project, are exempt from demolition project notification requirements, recorded from its source on 2026-08-15.

$0.10 per square foot of friable asbestos-containing materials plus $0.10 linear foot of friable asbestos-containing materials, with a minimum of $25 for any project; but not to exceed $50 for any small project or residential dwelling project nor exceed $1,000 for any other project.

— epd.georgia.gov, retrieved 2026-08-15

jurisdiction
Georgia our reading
delegated authority
Georgia Environmental Protection Division, Lead-Based Paint and Asbestos Program
notification trigger threshold
All demolitions regardless of asbestos amount; any project involving ten (10) or more continuous linear feet or ten (10) or more square feet of asbestos-containing material for renovations/abatement
advance notice days
ten (10) working day
notification fee
$0.10 per square foot of friable asbestos-containing materials plus $0.10 linear foot of friable asbestos-containing materials, with a minimum of $25 for any project; but not to exceed $50 for any small project or residential dwelling project nor exceed $1,000 for any other project verified
residential exemption
Legal owners or residences where four (4) or fewer dwelling units are involved, unless part of a larger project, are exempt from demolition project notification requirements
emergency notification rules
Notification of the emergency situation should be submitted within 24 hours from the time of its occurrence, or from the time you are contacted with a request for emergency work to be performed
statute or regulation citation
Georgia Department of Natural Resources Rules for Air Quality Control, Chapter 391-3-1-.02(9)(b)7; Georgia Rules of Asbestos Removal and Encapsulation, Chapter 391-3-14 our reading
Sourceepd.georgia.gov
Verified
Review by
DatasetAsbestos Abatement Notification Requirements, Thresholds, and Fees by State

Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.

Source

Last verified against source: . Due for re-check by . This page as Markdown · OKF bundle · full dataset as JSON.