Virginia
For Virginia, sol — contract (years) is 5; statute of repose (years) is 5; sor trigger event is substantial completion; statutory citation is Va. Code §8.01-250, verified against its source on 2026-11-19.
- State
- Virginia our reading
- SOL — contract (years)
- 5 verified
- Statute of repose (years)
- 5 verified
- SOR trigger event
- substantial completion verified
- Statutory citation
- Va. Code §8.01-250 verified
Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.
Cite as: Virginia — State construction defect statute of limitations and statute of repose periods (State construction defect statute of limitations and statute of repose periods), referencesource.org/state-construction-defect-limitations-periods/virginia/, checked 2026-11-19.
What the source says
Va. Code §8.01-250 — 5-year SOR from substantial completion. SOL 5 years for written contract (§8.01-246). Virginia's SOR is among the most contractor-favorable in the country and frequently dispositive on latent defect claims.
— terrapincg.com, retrieved 2026-08-18