Colorado
For Colorado, sol — contract (years) is 2; sol — tort (years) is 2; statute of repose (years) is 6; sor trigger event is substantial completion; discovery rule is Yes, recorded from its source on 2026-08-18.
- State
- Colorado our reading
- SOL — contract (years)
- 2 verified
- SOL — tort (years)
- 2 verified
- Statute of repose (years)
- 6 verified
- SOR trigger event
- substantial completion verified
- Discovery rule
- Yes our reading
- Statutory citation
- CRS §13-80-104 verified
Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.
What the source says
CRS §13-80-104 — 6-year SOR from substantial completion (extended to 8 years for claims accruing in years 5–6). SOL 2 years from discovery. Construction Defect Action Reform Act (CDARA) governs procedural pre-litigation steps.
— terrapincg.com, retrieved 2026-08-18
Source
- terrapincg.comhttps://terrapincg.com/news/construction-defect-statute-of-limitations-by-state-2026