New Mexico
What is the preliminary notice required for New Mexico?
For New Mexico, preliminary notice required is conditional — not required for GC or those contracting directly with GC; required for remote claimants on claims over $5,000 within 60 days of first furnishing; notice name is Notice of Right to Claim a Lien; notice deadline — gc (days) is not required; notice deadline — sub/supplier (days) is not required; lien recording deadline — gc (days) is 120, recorded from its source on 2026-08-14; source re-checked 2026-11-15.
Under §48-2-2.1, a mechanic or materialman who contracts with neither the owner nor the original contractor must serve a Notice of Right to Claim a Mechanic Lien within 60 days of first furnishing where the lien claim exceeds $5,000. An original contractor, and anyone contracting directly with the original contractor, is exempt, and the requirement does not reach residential property containing 4 or fewer dwelling units.
— mechanicslien.com, retrieved 2026-08-14
- State
- New Mexico
- Preliminary notice required
- conditional — not required for GC or those contracting directly with GC; required for remote claimants on claims over $5,000 within 60 days of first furnishing our reading
- Notice name
- Notice of Right to Claim a Lien
- Notice deadline — GC (days)
- not required
- Notice deadline — sub/supplier (days)
- not required
- Lien recording deadline — GC (days)
- 120
- Lien recording deadline — sub/supplier (days)
- 90
- Enforcement deadline (days)
- 730
- Late notice consequence
- partial our reading
- Statute
- N.M. Statutes §48-2-1 et seq.
Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.
Cite as: New Mexico — Mechanics lien filing deadlines, preliminary notice requirements, and enforcement windows by US state and party role (Mechanics lien filing deadlines, preliminary notice requirements, and enforcement windows by US state and party role), referencesource.org/mechanics-lien-deadlines-by-state/new-mexico/, checked 2026-11-15.
Source
- mechanicslien.comhttps://mechanicslien.com/new-mexico
Open the page on mechanicslien.com that states this — the page quoted above, at its publisher. Unpaid: we earn nothing from this link and it is not an advertisement.