For New Mexico, preliminary notice required is conditional — not required for GC or those contracting directly with GC; required for remote claimants on claims over $5,000 within 60 days of first furnishing; notice name is Notice of Right to Claim a Lien; notice deadline — gc (days) is not required; notice deadline — sub/supplier (days) is not required; lien recording deadline — gc (days) is 120, recorded from its source on 2026-08-14.

State
New Mexico
Preliminary notice required
conditional — not required for GC or those contracting directly with GC; required for remote claimants on claims over $5,000 within 60 days of first furnishing our reading
Notice name
Notice of Right to Claim a Lien
Notice deadline — GC (days)
not required
Notice deadline — sub/supplier (days)
not required
Lien recording deadline — GC (days)
120
Lien recording deadline — sub/supplier (days)
90
Enforcement deadline (days)
730
Late notice consequence
partial our reading
Statute
N.M. Statutes §48-2-1 et seq.
Sourcemechanicslien.com
Verified
Review by
DatasetMechanics lien filing deadlines, preliminary notice requirements, and enforcement windows by US state and party role

Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.

What the source says

Under §48-2-2.1, a mechanic or materialman who contracts with neither the owner nor the original contractor must serve a Notice of Right to Claim a Mechanic Lien within 60 days of first furnishing where the lien claim exceeds $5,000. An original contractor, and anyone contracting directly with the original contractor, is exempt, and the requirement does not reach residential property containing 4 or fewer dwelling units.