# New Mexico — Mechanics lien filing deadlines, preliminary notice requirements, and enforcement windows by US state and party role For New Mexico, preliminary notice required is conditional — not required for GC or those contracting directly with GC; required for remote claimants on claims over $5,000 within 60 days of first furnishing; notice name is Notice of Right to Claim a Lien; notice deadline — gc (days) is not required; notice deadline — sub/supplier (days) is not required; lien recording deadline — gc (days) is 120, recorded from its source on 2026-08-14. - **State:** New Mexico - **Preliminary notice required:** conditional — not required for GC or those contracting directly with GC; required for remote claimants on claims over $5,000 within 60 days of first furnishing _(our reading, not quoted from the source)_ - **Notice name:** Notice of Right to Claim a Lien - **Notice deadline — GC (days):** not required - **Notice deadline — sub/supplier (days):** not required - **Lien recording deadline — GC (days):** 120 - **Lien recording deadline — sub/supplier (days):** 90 - **Enforcement deadline (days):** 730 - **Late notice consequence:** partial _(our reading, not quoted from the source)_ - **Statute:** N.M. Statutes §48-2-1 et seq. ## What the source says > Under §48-2-2.1, a mechanic or materialman who contracts with neither the owner nor the original contractor must serve a Notice of Right to Claim a Mechanic Lien within 60 days of first furnishing where the lien claim exceeds $5,000. An original contractor, and anyone contracting directly with the original contractor, is exempt, and the requirement does not reach residential property containing 4 or fewer dwelling units. ## Source - https://mechanicslien.com/new-mexico Last verified: 2026-08-14. Review by: 2027-08-14. Part of [Mechanics lien filing deadlines, preliminary notice requirements, and enforcement windows by US state and party role](https://referencesource.org/mechanics-lien-deadlines-by-state/).