For New Hampshire, preliminary notice required is conditional — not required for GC; subs/suppliers without direct written contract with owner must notify owner before performing or furnishing; notice name is Notice of Lien; notice deadline — gc (days) is not required; notice deadline — sub/supplier (days) is before first furnishing; lien recording deadline — gc (days) is 120, recorded from its source on 2026-08-14.

State
New Hampshire
Preliminary notice required
conditional — not required for GC; subs/suppliers without direct written contract with owner must notify owner before performing or furnishing our reading
Notice name
Notice of Lien verified
Notice deadline — GC (days)
not required
Notice deadline — sub/supplier (days)
before first furnishing
Lien recording deadline — GC (days)
120
Lien recording deadline — sub/supplier (days)
120
Enforcement deadline (days)
120
Late notice consequence
partial our reading
Statute
N.H. RSA §447:1 et seq.
Sourcemechanicslien.com
Verified
Review by
DatasetMechanics lien filing deadlines, preliminary notice requirements, and enforcement windows by US state and party role

Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.

What the source says

Serve a written Notice of Lien on the owner before performing labor, or in writing before furnishing materials. Required for any claimant not in direct contract with the owner. The Notice of Lien preserves lien rights against the owner; without it, the lien is limited to amounts the owner owes the prime contractor at the time notice is given.