Nevada

For Nevada, preliminary notice required is conditional — not required for GC; required for subs/suppliers within 31 days of first furnishing; notice name is Notice of Right to Lien; notice deadline — gc (days) is not required; notice deadline — sub/supplier (days) is 31; lien recording deadline — gc (days) is 90, recorded from its source on 2026-08-14.

State
Nevada
Preliminary notice required
conditional — not required for GC; required for subs/suppliers within 31 days of first furnishing our reading
Notice name
Notice of Right to Lien verified
Notice deadline — GC (days)
not required
Notice deadline — sub/supplier (days)
31 verified
Lien recording deadline — GC (days)
90
Lien recording deadline — sub/supplier (days)
90
Enforcement deadline (days)
180
Late notice consequence
partial our reading
Statute
NRS §108.221 et seq.
Sourcemechanicslien.com
Verified
Review by
DatasetMechanics lien filing deadlines, preliminary notice requirements, and enforcement windows by US state and party role

Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.

What the source says

Serve a Notice of Right to Lien on the owner and the prime contractor within 31 days of first delivery of labor or materials. The 31 days is a look-back, not a cutoff. The notice may be served at any time, and a late one still preserves lien rights for the 31 days before it is served plus everything furnished after. NRS §108.245(1), (6).

mechanicslien.com, retrieved 2026-08-14