Washington

For Washington, owner-to-gc payment deadline (days) is 30; gc-to-sub flow-down deadline (days) is 10; late-payment interest rate is 1% per month; project types covered is public; attorney fees recoverable is yes, verified against its source on 2026-08-15.

State
Washington verified
Owner-to-GC payment deadline (days)
30 verified
GC-to-sub flow-down deadline (days)
10 verified
Late-payment interest rate
1% per month verified
Project types covered
public verified
Attorney fees recoverable
yes verified
Statutory citation
Wash. Rev. Code §§ 39.76.011-39.76.040 and 39.04.250 verified
Sourcelevelset.com
Verified
Review by
DatasetConstruction prompt payment act deadlines by US state — owner-to-contractor and contractor-to-subcontractor payment windows, retention release deadlines, and late-payment interest rates

What the source says

Washington does not have any prompt payment provisions regarding private projects. Therefore, the timing of payments and penalties will be governed by the terms of the contract.