For West Virginia, owner-to-gc payment deadline (days) is 60; project types covered is public; attorney fees recoverable is no; statutory citation is W. Va. Code §§ 7-5-7, 8-13-22d, and 14-3-1, recorded from its source on 2026-08-15; source re-checked 2026-09-29.

State
West Virginia verified
Owner-to-GC payment deadline (days)
60
Project types covered
public
Attorney fees recoverable
no our reading
Statutory citation
W. Va. Code §§ 7-5-7, 8-13-22d, and 14-3-1
Sourcelevelset.com
Verified
Review by
DatasetConstruction prompt payment act deadlines by US state — owner-to-contractor and contractor-to-subcontractor payment windows, retention release deadlines, and late-payment interest rates

Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.

What the source says

West Virginia does not provide a prompt payment for private projects.

— levelset.com, retrieved 2026-08-15