Virginia

For Virginia, owner-to-gc payment deadline (days) is 30; gc-to-sub flow-down deadline (days) is 7; late-payment interest rate is 1% per month; project types covered is public; attorney fees recoverable is no, recorded from its source on 2026-08-15; source re-checked 2026-11-17.

State
Virginia
Owner-to-GC payment deadline (days)
30 verified
GC-to-sub flow-down deadline (days)
7
Late-payment interest rate
1% per month
Project types covered
public verified
Attorney fees recoverable
no our reading
Statutory citation
Va. Code §§ 2.2-4347 – 2.2-4356
Sourcelevelset.com
Verified
Review by
DatasetConstruction prompt payment act deadlines by US state — owner-to-contractor and contractor-to-subcontractor payment windows, retention release deadlines, and late-payment interest rates

Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.

Cite as: Virginia — Construction prompt payment act deadlines by US state — owner-to-contractor and contractor-to-subcontractor payment windows, retention release deadlines, and late-payment interest rates (Construction prompt payment act deadlines by US state — owner-to-contractor and contractor-to-subcontractor payment windows, retention release deadlines, and late-payment interest rates), referencesource.org/construction-prompt-payment-deadlines-by-state/virginia/, checked 2026-11-17.

What the source says

On state projects, the prime contractor must be paid 30 days after the public agency receives a proper invoice or 30 days after the receipt of labor or materials on the project; whichever is later.

— levelset.com, retrieved 2026-08-15