Newman unit 4, TX — planned retirement, EIA data for May 2026
For Newman unit 4, TX, planned retirement year is 2031; planned retirement month is 12; net summer capacity (mw) is 86.0; technology is Natural Gas Fired Combined Cycle; fuel code is NG; operator is El Paso Electric Co, verified against its source on 2026-09-24.
- Plant
- Newman verified
- EIA plant ID
- 3456 verified
- Generator ID
- 4 verified
- Planned retirement year
- 2031 verified
- Planned retirement month
- 12 verified
- Operator
- El Paso Electric Co verified
- EIA entity ID
- 5701 verified
- Producer type
- Electric Utility verified
- State
- TX verified
- Net summer capacity (MW)
- 86.0 verified
- Technology
- Natural Gas Fired Combined Cycle verified
- Fuel code
- NG verified
- Prime mover
- CA verified
- EPM edition
- May 2026 verified
What the source says
2031 12 5701 El Paso Electric Co Electric Utility Newman TX 3456 4 86.0 Natural Gas Fired Combined Cycle NG CA
— eia.gov, retrieved 2026-09-24
Where each value comes from
The value above is stated away from the sentence quoted with the answer, so the passage that states it is shown here too.
EPM edition
Table 1.1. Net Generation by Energy Source: Total (All Sectors), 2016-May 2026
— all from eia.gov, retrieved 2026-09-24
Source
- eia.govhttps://www.eia.gov/electricity/monthly/archive/july2026.pdf