West Virginia
What is the preliminary notice required for West Virginia?
For West Virginia, preliminary notice required is conditional — not required for GC; subcontractors and suppliers not in privity with owner must serve notice to owner within 30 days of first furnishing; notice name is Notice of Mechanic's Lien; notice deadline — gc (days) is not required; notice deadline — sub/supplier (days) is 30; lien recording deadline — gc (days) is 100, recorded from its source on 2026-08-14; source re-checked 2026-11-15.
W. Va. Code §38-2-1 et seq. — Private Works, Notice to Owner & Public Project Bond Claims Create Your Account File a Claim <tel:+18004327799> Call (800) 432-7799 Free WV Deadline Calculator Calculate your West Virginia deadlines and get a free consultation. West Virginia mechanic lien deadline table with toggles for project type and claimant type. West Virginia Preliminary Notice & Mechanic Lien Deadlines Select your project type and role to see the deadlines that apply to you. Project Type Private Projects Public Works Select Your Tier Prime Contractor Subcontractors & Suppliers Remote Claimants Prime Contractor — In privity with the property owner Preliminary Notice Mechanic Lien Enforcement Not Required 100
— mechanicslien.com, retrieved 2026-08-14
- State
- West Virginia verified
- Preliminary notice required
- conditional — not required for GC; subcontractors and suppliers not in privity with owner must serve notice to owner within 30 days of first furnishing our reading
- Notice name
- Notice of Mechanic's Lien
- Notice deadline — GC (days)
- not required verified
- Notice deadline — sub/supplier (days)
- 30
- Lien recording deadline — GC (days)
- 100 verified
- Lien recording deadline — sub/supplier (days)
- 100 verified
- Enforcement deadline (days)
- 180
- Late notice consequence
- forfeiture our reading
- Statute
- W. Va. Code §38-2-1 et seq. verified
Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.
Cite as: West Virginia — Mechanics lien filing deadlines, preliminary notice requirements, and enforcement windows by US state and party role (Mechanics lien filing deadlines, preliminary notice requirements, and enforcement windows by US state and party role), referencesource.org/mechanics-lien-deadlines-by-state/west-virginia/, checked 2026-11-15.
Source
- mechanicslien.comhttps://mechanicslien.com/west-virginia