For Tennessee, preliminary notice required is conditional — required on commercial projects for remote contractors (Notice of Nonpayment within 90 days of end of each month with unpaid work); not required for prime contractors; notice name is Notice of Nonpayment; notice deadline — gc (days) is not required; notice deadline — sub/supplier (days) is 90; lien recording deadline — gc (days) is 365, recorded from its source on 2026-08-14.

State
Tennessee verified
Preliminary notice required
conditional — required on commercial projects for remote contractors (Notice of Nonpayment within 90 days of end of each month with unpaid work); not required for prime contractors our reading
Notice name
Notice of Nonpayment verified
Notice deadline — GC (days)
not required verified
Notice deadline — sub/supplier (days)
90 verified
Lien recording deadline — GC (days)
365
Lien recording deadline — sub/supplier (days)
90 verified
Enforcement deadline (days)
90 verified
Late notice consequence
partial our reading
Statute
T.C.A. § 66-11-101 et seq.
Sourcemechanicslien.com
Verified
Review by
DatasetMechanics lien filing deadlines, preliminary notice requirements, and enforcement windows by US state and party role

Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.

What the source says

File a Lawsuit Tennessee private project deadlines Prime Contractor Preliminary Notice: Not required. A prime contractor in direct contract with the owner has no preliminary notice obligation. Mechanic Lien: The prime contractor's mechanic lien against the owner arises automatically upon furnishing and remains enforceable for 1 year after completion without any recording. To preserve priority against subsequent purchasers and encumbrancers, record a Notice of Lien (Sworn Statement of amount owed) with the County Register within 1 year after completion of the contract. Enforcement: Commence an action to enforce the mechanic lien within 1 year after completion of the contract. Subcontractors & Suppliers Preliminary Notice: On commercial projects, serve a Notice of Nonpayment on the owner and prime contractor by certified mail within 90 days after the last day of each month in which labor or materials were furnished and remain unpaid.