For Pennsylvania, preliminary notice required is conditional — not required for GC; for subs on projects of $1.5 million or more where owner has filed Notice of Commencement, Notice of Furnishing must be filed within 45 days of first furnishing; all subs must also serve 30-day Notice of Intent to Lien before filing; notice name is Notice of Furnishing; notice deadline — gc (days) is not required; notice deadline — sub/supplier (days) is 45; lien recording deadline — gc (days) is 180, recorded from its source on 2026-08-14.

State
Pennsylvania verified
Preliminary notice required
conditional — not required for GC; for subs on projects of $1.5 million or more where owner has filed Notice of Commencement, Notice of Furnishing must be filed within 45 days of first furnishing; all subs must also serve 30-day Notice of Intent to Lien before filing our reading
Notice name
Notice of Furnishing verified
Notice deadline — GC (days)
not required verified
Notice deadline — sub/supplier (days)
45
Lien recording deadline — GC (days)
180
Lien recording deadline — sub/supplier (days)
180
Enforcement deadline (days)
730
Late notice consequence
forfeiture our reading
Statute
49 P.S. §1101 et seq. verified
Sourcemechanicslien.com
Verified
Review by
DatasetMechanics lien filing deadlines, preliminary notice requirements, and enforcement windows by US state and party role

Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.

What the source says

49 P.S. §1101 et seq. — Private Works, Notice of Furnishing & Public Project Bond Claims <https://app.mechanicslien.com/?mode=sign-up> Create Your Account <https://www.mechanicslien.com/get-help/pennsylvania> File a Claim <tel:+18004327799> Call (800) 432-7799 Free PA Deadline Calculator Calculate your Pennsylvania deadlines and get a free consultation. Pennsylvania mechanic lien deadline table with toggles for project type and claimant type. Pennsylvania Preliminary Notice & Mechanic Lien Deadlines Select your project type and role to see the deadlines that apply to you. Project Type Private Projects Public Works Select Your Tier Prime Contractor Subcontractors & Suppliers Remote Claimants Prime Contractor — In privity with the property owner Preliminary Notice Mechanic Lien Enforcement Not Required

mechanicslien.com, retrieved 2026-08-14

Source

Last verified against source: . Due for re-check by . This page as Markdown · OKF bundle · full dataset as JSON.