Michigan

For Michigan, preliminary notice required is conditional — not required for GC; subcontractors and suppliers must serve Notice of Furnishing within 20 days of first furnishing; notice name is Notice of Furnishing; notice deadline — gc (days) is not required; notice deadline — sub/supplier (days) is 20; lien recording deadline — gc (days) is 90, recorded from its source on 2026-08-14.

State
Michigan verified
Preliminary notice required
conditional — not required for GC; subcontractors and suppliers must serve Notice of Furnishing within 20 days of first furnishing our reading
Notice name
Notice of Furnishing verified
Notice deadline — GC (days)
not required
Notice deadline — sub/supplier (days)
20 verified
Lien recording deadline — GC (days)
90 verified
Lien recording deadline — sub/supplier (days)
90 verified
Enforcement deadline (days)
365
Late notice consequence
partial — Late service does not destroy lien rights but limits the lien to labor or materials furnished within the 20-day lookback period before service our reading
Statute
M.C.L.A. §570.1101 et seq. verified
Sourcemechanicslien.com
Verified
Review by
DatasetMechanics lien filing deadlines, preliminary notice requirements, and enforcement windows by US state and party role

Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.

What the source says

90-day Claim of Mechanic Lien recording deadline, owner service requirements, and filing procedures under M.C.L.A. §570.1101 Learn More <https://www.mechanicslien.com/michigan/lien-enforcement-deadlines> Mechanic Lien Enforcement Deadlines 1-year suit deadline, Lis Pendens filing, public bond claim enforcement, and highway project suit timelines Learn More Related Reading In-Depth Michigan Guides <https://www.mechanicslien.com/blog/notice-of-commencement-michigan> How Important is Filing a Notice of Commencement in Michigan? Michigan requires a Notice of Commencement filed with the registrar of deeds and posted at the worksite. Read the Guide Frequently Asked Questions What statute governs mechanic liens in Michigan? Private works construction mechanic lien rights are governed by the Michigan Construction Mechanic Lien Act, M.C.L.A. §570.1101 et seq. Public municipal bond claims fall under M.C.L.A. §129.201 et seq. Highway project bond claims are under M.C.L.A. §570.101 et seq. What is the Notice of Furnishing in Michigan? Subcontractors, suppliers, and laborers must serve a Notice of Furnishing within 20 days of first delivery or furnishing under M.C.L.A.

mechanicslien.com, retrieved 2026-08-14

Source

Last verified against source: . Due for re-check by . This page as Markdown · OKF bundle · full dataset as JSON.