Kansas
For Kansas, preliminary notice required is conditional — not required on commercial projects; Warning Statement required for subs/suppliers on residential before furnishing; Notice of Intent to Perform required for subs on residential; notice name is Warning Statement; notice deadline — gc (days) is not required; notice deadline — sub/supplier (days) is not required; lien recording deadline — gc (days) is 4 months, recorded from its source on 2026-08-14.
- State
- Kansas verified
- Preliminary notice required
- conditional — not required on commercial projects; Warning Statement required for subs/suppliers on residential before furnishing; Notice of Intent to Perform required for subs on residential our reading
- Notice name
- Warning Statement verified
- Notice deadline — GC (days)
- not required verified
- Notice deadline — sub/supplier (days)
- not required verified
- Lien recording deadline — GC (days)
- 4 months verified
- Lien recording deadline — sub/supplier (days)
- 3 months verified
- Enforcement deadline (days)
- 1 year
- Late notice consequence
- forfeiture our reading
- Statute
- K.S.A. §60-1101 to §60-1112 verified
Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.
What the source says
Mechanic liens on private construction projects in Kansas are governed by Kansas General Statutes K.S.A. §60-1101 to §60-1112. Public works payment bond claims are also governed by K.S.A. §60-1110 to §60-1112, which require a minimum 100% payment bond. Is a preliminary notice required to file a mechanic lien in Kansas? For general contractors, no preliminary notice is required. For subcontractors and material suppliers on residential projects, a warning statement must be mailed to the property owner before performance under K.S.A. §60-1103a. The warning statement is not required if the claim does not exceed $250. What is the deadline to file a mechanic lien in Kansas? Contractors must record a Contractor's Mechanic Lien Statement within 4 months after last performance (extendable to 5 months on non-residential property). Subcontractors must record within 3 months (extendable to 5 months on non-residential property).
— mechanicslien.com, retrieved 2026-08-14
Source
- mechanicslien.comhttps://mechanicslien.com/kansas