Indiana

For Indiana, preliminary notice required is conditional — not required on commercial projects; Pre-Lien Notice required for subs/suppliers within 30 days of first furnishing on Class 2 residential projects; notice name is Pre-Lien Notice; notice deadline — gc (days) is not required; notice deadline — sub/supplier (days) is 30; lien recording deadline — gc (days) is 90, recorded from its source on 2026-08-14.

State
Indiana
Preliminary notice required
conditional — not required on commercial projects; Pre-Lien Notice required for subs/suppliers within 30 days of first furnishing on Class 2 residential projects our reading
Notice name
Pre-Lien Notice verified
Notice deadline — GC (days)
not required
Notice deadline — sub/supplier (days)
30 verified
Lien recording deadline — GC (days)
90
Lien recording deadline — sub/supplier (days)
90
Enforcement deadline (days)
1 year
Late notice consequence
partial our reading
Statute
Indiana Code §32-28-3-1
Sourcemechanicslien.com
Verified
Review by
DatasetMechanics lien filing deadlines, preliminary notice requirements, and enforcement windows by US state and party role

Values marked our reading are our classification of what the source says — the source does not print them in those words. The quote below is the evidence for each one; judge it yourself.

What the source says

Class 2 residential projects (owner-occupied single or double family dwellings): serve a Pre-Lien Notice on the owner within 30 days after first furnishing labor or materials. Missing this deadline forfeits lien rights on materials furnished before service. Commercial projects: no pre-lien notice is required.

mechanicslien.com, retrieved 2026-08-14